Assessment Year | 2019 |
---|---|
Principal Product | Bottled Water Equipment |
NAICS | 312112: Bottled Water Manufacturing |
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
115,000
ft2
|
Annual Production | 1,100
units
|
Production Hrs. Annual | 2,730
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $30,495 | 850,360 |
kWh
|
$0.036 | |
Electricity Demand | $51,858 | 4,086 |
kW-mo/yr
|
$12.69 | |
Natural Gas | $16,458 | 1,269 |
MMBtu
|
$12.97 | |
Waste Disposal Costs | |||||
Water Usage | $6,043 | 1,977 |
Tgal
|
$3.06 | |
Water Disposal | $6,063 | 1,977 |
Tgal
|
$3.07 | |
TOTAL YEARLY COSTS | $110,917 | ||||
RECOMMENDED SAVINGS* | $24,406 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $12,124 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,764 | $8,337 |
$4,173
115,905
kWh
|
$7,592
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7243: Improve air circulation with destratification fans / other methods | $9,862 | $11,390 |
$(-190.3)
(-5,286)
kWh
|
$(-448.0)
-
kW-mo/yr
|
- | - | - | $10,500 | |
03 | 2.7135: Install occupancy sensors | $1,679 | $4,388 |
$594
16,584
kWh
|
$1,085
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.8114: Change rate schedules or other changes in utility service | $493 | - | - | - |
$493
-
Tgal
|
- | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $248 | - |
$248
6,924
kWh
|
- | - | - | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $238 | $500 |
$438
12,182
kWh
|
- | - | $(-100.0) | $(-100.0) | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $122 | $275 |
$122
3,393
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $24,406 | $24,890 |
$5,384
149,702
kWh
|
$8,229
-
kW-mo/yr
|
$493
-
Tgal
|
$(-100.0) | $(-100.0) | $10,500 | ||
TOTAL IMPLEMENTED | $12,124 | $9,112 |
$4,733
131,480
kWh
|
$7,592
-
kW-mo/yr
|
- | $(-100.0) | $(-100.0) | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs