| Assessment Year | 2019 |
|---|---|
| Principal Product | Compressed Natural Gas Tanks for Large Vehicle Use |
| NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $5 M to 10M |
| # of Employees | 130 |
| Plant Area |
121,000
ft2
|
| Annual Production | 750
units
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Nebraska |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $40,751 | 1,557,162 |
kWh
|
$0.026 | |
| Electricity Demand | $78,754 | 3,759 |
kW-mo/yr
|
$20.95 | |
| Electricity Fees | $15,202 | - |
|
- | |
| Natural Gas | $49,743 | 6,726 |
MMBtu
|
$7.40 | |
| Waste Disposal Costs | |||||
| Other Liquid (haz) | $16,200 | 1,320 |
gal
|
$12.27 | |
| TOTAL YEARLY COSTS | $200,650 | ||||
| RECOMMENDED SAVINGS* | $44,652 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $13,506 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4226: Use / purchase optimum sized compressor | $31,146 | $40,000 |
$1,659
63,809
kWh
|
$29,487
-
kW-mo/yr
|
- | |
| 02 | 3.7197: Use ultrasonic cleaning | $13,380 | $15,575 |
$(-105.3)
(-4,050)
kWh
|
$(-2,715.1)
-
kW-mo/yr
|
$16,200
-
gal
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $126 | $500 |
$126
4,885
kWh
|
- | - | |
| TOTAL RECOMMENDED | $44,652 | $56,075 |
$1,680
64,644
kWh
|
$26,772
-
kW-mo/yr
|
$16,200
-
gal
|
||
| TOTAL IMPLEMENTED | $13,506 | $16,075 |
$21
835
kWh
|
$(-2,715.1)
-
kW-mo/yr
|
$16,200
-
gal
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs