Assessment Year | 2018 |
---|---|
Principal Product | Compressed Natural Gas Tanks for Large Vehicle Use |
NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $50 M to 100M |
# of Employees | 130 |
Plant Area |
108,000
ft2
|
Annual Production | 30,000
units
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $151,368 | 5,792,800 |
kWh
|
$0.026 | |
Electricity Demand | $206,851 | 10,825 |
kW-mo/yr
|
$19.11 | |
Electricity Fees | $86,616 | - |
|
- | |
Natural Gas | $90,719 | 13,663 |
MMBtu
|
$6.64 | |
Waste Disposal Costs | |||||
Water Usage | $47,169 | 15,667 |
Tgal
|
$3.01 | |
Water Disposal | $46,415 | 15,667 |
Tgal
|
$2.96 | |
TOTAL YEARLY COSTS | $629,139 | ||||
RECOMMENDED SAVINGS* | $49,070 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $43,963 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 3.4114: Replace city water with recycled water via cooling tower | $24,797 | $32,620 |
$(-1,123.0)
(-43,200)
kWh
|
- |
$12,960
-
Tgal
|
$12,960
-
Tgal
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $18,840 | $74,980 |
$11,091
426,585
kWh
|
$10,709
-
kW-mo/yr
|
- | - | $(-2,960.0) | |
03 | 2.2511: Insulate bare equipment | $4,500 | $2,500 |
$2,264
87,000
kWh
|
$2,236
-
kW-mo/yr
|
- | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $607 | $1,050 |
$607
23,339
kWh
|
- | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $326 | $1,000 |
$452
17,636
kWh
|
- | - | - | $(-126.0) | |
TOTAL RECOMMENDED | $49,070 | $112,150 |
$13,291
511,360
kWh
|
$12,945
-
kW-mo/yr
|
$12,960
-
Tgal
|
$12,960
-
Tgal
|
$(-3,086.0) | ||
TOTAL IMPLEMENTED | $43,963 | $108,600 |
$10,420
401,021
kWh
|
$10,709
-
kW-mo/yr
|
$12,960
-
Tgal
|
$12,960
-
Tgal
|
$(-3,086.0) |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs