| Assessment Year | 2014 |
|---|---|
| Principal Product | Polyvinyl Chloride Resin |
| NAICS | 325211: Plastics Material and Resin Manufacturing |
| SIC | 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers |
| Sales Range | $50 M to 100M |
| # of Employees | 110 |
| Plant Area |
400,000
ft2
|
| Annual Production | 53,000
ton
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Delaware |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $2,906,828 | 42,054,712 |
kWh
|
$0.069 |
| Natural Gas | $2,701,671 | 557,281 |
MMBtu
|
$4.85 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $149,650 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $106,350 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $59,000 | $150,000 |
$59,000
855,000
kWh
|
- | |
| 02 | 2.1113: Reduce combustion air flow to optimum | $28,000 | $50,000 | - |
$28,000
-
MMBtu
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $23,150 | $101,600 |
$23,150
335,500
kWh
|
- | |
| 04 | 2.2511: Insulate bare equipment | $18,200 | $12,560 | - |
$18,200
-
MMBtu
|
|
| 05 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $6,000 | $20,000 | - |
$6,000
-
MMBtu
|
|
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $15,300 | $15,000 |
$15,300
222,220
kWh
|
- | |
| TOTAL RECOMMENDED | $149,650 | $349,160 |
$97,450
1,412,720
kWh
|
$52,200
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $106,350 | $284,160 |
$82,150
1,190,500
kWh
|
$24,200
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs