| Assessment Year | 2017 |
|---|---|
| Principal Product | Injection Molded Plastics |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 120 |
| Plant Area |
80,000
ft2
|
| Annual Production | 612,500,000
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Nebraska |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $317,795 | 12,400,000 |
kWh
|
$0.026 | |
| Electricity Demand | $506,923 | 24,775 |
kW-mo/yr
|
$20.46 | |
| Electricity Fees | $45,156 | - |
|
- | |
| Waste Disposal Costs | |||||
| Water Usage | $8,934 | 799,600 |
Tgal
|
$0.011 | |
| Water Disposal | $13,408 | 742 |
Tgal
|
$18.08 | |
| TOTAL YEARLY COSTS | $892,217 | ||||
| RECOMMENDED SAVINGS* | $22,794 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $22,534 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $9,200 | $1,630 |
$9,200
323,000
kWh
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,430 | $12,500 |
$3,072
120,000
kWh
|
$4,358
-
kW-mo/yr
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,100 | - |
$4,700
183,000
kWh
|
- | $(-600.0) | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,804 | $2,500 |
$553
21,580
kWh
|
$1,251
-
kW-mo/yr
|
- | |
| 05 | 2.7135: Install occupancy sensors | $260 | $225 |
$260
10,156
kWh
|
- | - | |
| TOTAL RECOMMENDED | $22,794 | $16,855 |
$17,785
657,736
kWh
|
$5,609
-
kW-mo/yr
|
$(-600.0) | ||
| TOTAL IMPLEMENTED | $22,534 | $16,630 |
$17,525
647,580
kWh
|
$5,609
-
kW-mo/yr
|
$(-600.0) | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs