Assessment Year | 2017 |
---|---|
Principal Product | treatment wastewater |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $500 k to 1M |
# of Employees | 3 |
Plant Area |
8,000
ft2
|
Annual Production | 657,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $138,432 | 150,000 |
kWh
|
$0.92 | |
Natural Gas | $1,700 | 145 |
MMBtu
|
$11.72 | |
Waste Disposal Costs | |||||
Other Liquid (non-haz) | $1,300 | 21 |
gal
|
$61.90 | |
TOTAL YEARLY COSTS | $141,432 | ||||
RECOMMENDED SAVINGS* | $25,821 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $1,585 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Other Liquid (haz) Savings |
---|---|---|---|---|---|---|
01 | 3.1191: Change procedures / equipment / operating conditions | $17,000 | $20,000 |
$15,800
78,000
kWh
|
$1,200
-
gal
|
|
02 | 2.4133: Use most efficient type of electric motors | $360 | $1,000 |
$360
7,500
kWh
|
- | |
03 | 2.7134: Use photocell controls | $1,225 | $2,000 |
$1,225
8,000
kWh
|
- | |
04 | 2.6231: Utilize controls to operate equipment only when needed | $7,236 | $40,000 |
$7,236
103,914
kWh
|
- | |
TOTAL RECOMMENDED | $25,821 | $63,000 |
$24,621
197,414
kWh
|
$1,200
-
gal
|
||
TOTAL IMPLEMENTED | $1,585 | $3,000 |
$1,585
15,500
kWh
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs