Assessment Year | 1998 |
---|---|
Principal Product | Carpet |
NAICS |
n/a
|
SIC | 2273: Carpets and Rugs |
Sales Range | $10 M to 50M |
# of Employees | 225 |
Plant Area |
350,000
ft2
|
Annual Production | 1,850,000
pieces
|
Production Hrs. Annual | 2,500
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $67,800 | 2,520,516 |
kWh
|
$0.027 |
Electricity Demand | $119,375 | 9,084 |
kW-mo/yr
|
$13.14 |
Electricity Fees | $14,448 | - |
|
- |
Natural Gas | $198,614 | 64,378 |
MMBtu
|
$3.09 |
LPG | $16,549 | 2,613 |
MMBtu
|
$6.33 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $312,199 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8112: Combine utility meters | $10,670 | - | n/a | - | - | - | - | - | - | $10,670 | - | - | - |
02 | 2.4226: Use / purchase optimum sized compressor | $8,406 | $5,000 | n/a |
$2,370
87,925
kWh
|
$5,560
-
kW-mo/yr
|
$476 | - | - | - | - | - | - | - |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $3,573 | - | n/a | - | - | - |
$4,473
-
MMBtu
|
- | $(-900.0) | - | - | - | - |
04 | 4.114: Add/modify equipment to improve drying process | $200,000 | - | n/a | - | - | - | - | - | - | - | - | - | $200,000 |
05 | 2.2514: Cover open tanks | $66,490 | $87,860 | n/a | - | - | - |
$40,900
-
MMBtu
|
$25,150
-
Tgal
|
- | - | $440 | - | - |
06 | 2.2414: Use waste heat from hot flue gases to preheat | $6,600 | $10,500 | n/a | - | - | - |
$6,600
-
MMBtu
|
- | - | - | - | - | - |
07 | 2.2437: Recover waste heat from equipment | $1,800 | $1,000 | n/a | - | - | - |
$1,800
-
MMBtu
|
- | - | - | - | - | - |
08 | 3.4155: Meter waste water | $1,180 | $2,350 | n/a | - | - | - | - | - | - | - | - |
$1,180
-
Tgal
|
- |
09 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $13,480 | - | n/a | - | - | - | - | - | - | - | $13,480 | - | - |
TOTAL RECOMMENDED | $312,199 | $106,710 |
$2,370
87,925
kWh
|
$5,560
-
kW-mo/yr
|
$476 |
$53,773
-
MMBtu
|
$25,150
-
Tgal
|
$(-900.0) | $10,670 | $13,920 |
$1,180
-
Tgal
|
$200,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs