Assessment Year | 2000 |
---|---|
Principal Product | injection manifolds and liquid reservoirs |
NAICS |
n/a
|
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
120,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $259,150 | 7,229,191 |
kWh
|
$0.036 |
Electricity Demand | $130,843 | 13,830 |
kW-mo/yr
|
$9.46 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $21,613 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,985 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $17,460 | $200 |
$6,758
188,453
kWh
|
$12,487
-
kW-mo/yr
|
- | $(-1,785.0) | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $76 | $150 |
$27
879
kWh
|
$9
-
kW-mo/yr
|
- | - | $40 | |
03 | 2.7135: Install occupancy sensors | $460 | $200 |
$336
9,379
kWh
|
$124
-
kW-mo/yr
|
- | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $1,647 | $1,000 |
$1,390
38,687
kWh
|
$257
-
kW-mo/yr
|
- | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $491 | $40 |
$491
13,775
kWh
|
- | - | - | - | |
06 | 3.4151: Minimize water usage | $445 | $1,330 | - | - |
$445
-
Tgal
|
- | - | |
07 | 4.611: Begin a practice of predictive / preventative maintenance | $1,034 | - | - | - | - | $1,034 | - | |
TOTAL RECOMMENDED | $21,613 | $2,920 |
$9,002
251,173
kWh
|
$12,877
-
kW-mo/yr
|
$445
-
Tgal
|
$(-751.0) | $40 | ||
TOTAL IMPLEMENTED | $18,985 | $240 |
$7,249
202,228
kWh
|
$12,487
-
kW-mo/yr
|
- | $(-751.0) | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs