Assessment Year | 2000 |
---|---|
Principal Product | Engine & Transmission Parts |
NAICS |
n/a
|
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 85 |
Plant Area |
50,000
ft2
|
Annual Production | 60,000
pieces
|
Production Hrs. Annual | 2,288
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $78,824 | 2,527,843 |
kWh
|
$0.031 |
Electricity Demand | $53,368 | 4,963 |
kW-mo/yr
|
$10.75 |
Electricity Fees | $6,696 | - |
|
- |
Natural Gas | $8,884 | 1,646 |
MMBtu
|
$5.40 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $22,626 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,530 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $858 | $195 |
$858
29,015
kWh
|
- | - | - | |
02 | 2.4151: Develop a repair/replace policy | $4,437 | $17,206 |
$2,971
78,546
kWh
|
$1,466
-
kW-mo/yr
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $207 | $280 |
$96
2,052
kWh
|
$31
-
kW-mo/yr
|
- | $80 | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,477 | $8,551 |
$536
18,171
kWh
|
$941
-
kW-mo/yr
|
- | - | |
05 | 2.7135: Install occupancy sensors | $721 | $800 |
$600
13,482
kWh
|
$121
-
kW-mo/yr
|
- | - | |
06 | 2.3212: Optimize plant power factor | $879 | $614 | - | - | $879 | - | |
07 | 2.8112: Combine utility meters | $8,059 | $40,000 | - | - | $8,059 | - | |
08 | 4.821: Pay bills on time to avoid late fees | $408 | - | - | - | $408 | - | |
09 | 4.811: Demolish old building to reduce tax and insurance bills | $5,580 | $250 | - | - | $5,580 | - | |
TOTAL RECOMMENDED | $22,626 | $67,896 |
$5,061
141,266
kWh
|
$2,559
-
kW-mo/yr
|
$14,926 | $80 | ||
TOTAL IMPLEMENTED | $8,530 | $9,276 |
$1,490
49,238
kWh
|
$972
-
kW-mo/yr
|
$5,988 | $80 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs