Assessment Year | 2000 |
---|---|
Principal Product | Aluminum Die Casts |
NAICS |
n/a
|
SIC | 3365: Aluminum Foundries |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
116,000
ft2
|
Annual Production | 10,000,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $159,059 | 10,425,557 |
kWh
|
$0.015 |
Electricity Demand | $253,839 | 20,996 |
kW-mo/yr
|
$12.09 |
Natural Gas | $222,715 | 63,195 |
MMBtu
|
$3.52 |
LPG | $15,100 | 940 |
MMBtu
|
$16.06 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,601 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2442: Preheat combustion air with waste heat | $1,922 | $8,000 |
$(-85.0)
(-5,569)
kWh
|
$(-133.0)
-
kW-mo/yr
|
$2,140
-
MMBtu
|
- | |
02 | 2.1331: Burn a less expensive grade of fuel | $11,307 | $39,100 |
$(-182.0)
(-12,016)
kWh
|
$(-276.0)
-
kW-mo/yr
|
$(-3,335.0)
-
MMBtu
|
$15,100
-
MMBtu
|
|
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $164 | $400 |
$139
9,086
kWh
|
$163
-
kW-mo/yr
|
$(-138.0)
-
MMBtu
|
- | |
04 | 2.6121: Reduce hot water temperature to the minimum required | $67 | $30 |
$67
4,689
kWh
|
- | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $1,996 | $300 |
$842
55,100
kWh
|
$1,154
-
kW-mo/yr
|
- | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,588 | $555 |
$1,588
104,045
kWh
|
- | - | - | |
07 | 2.7111: Reduce illumination to minimum necessary levels | $1,479 | $280 |
$586
38,394
kWh
|
$893
-
kW-mo/yr
|
- | - | |
08 | 2.7135: Install occupancy sensors | $78 | $200 |
$31
2,052
kWh
|
$47
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $18,601 | $48,865 |
$2,986
195,781
kWh
|
$1,848
-
kW-mo/yr
|
$(-1,333.0)
-
MMBtu
|
$15,100
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs