| Assessment Year | 2000 |
|---|---|
| Principal Product | Aluminum Die Casts |
| NAICS |
n/a
|
| SIC | 3365: Aluminum Foundries |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
116,000
ft2
|
| Annual Production | 10,000,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $159,059 | 10,425,557 |
kWh
|
$0.015 |
| Electricity Demand | $253,839 | 20,996 |
kW-mo/yr
|
$12.09 |
| Natural Gas | $222,715 | 63,195 |
MMBtu
|
$3.52 |
| LPG | $15,100 | 940 |
MMBtu
|
$16.06 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,601 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2442: Preheat combustion air with waste heat | $1,922 | $8,000 |
$(-85.0)
(-5,569)
kWh
|
$(-133.0)
-
kW-mo/yr
|
$2,140
-
MMBtu
|
- | |
| 02 | 2.1331: Burn a less expensive grade of fuel | $11,307 | $39,100 |
$(-182.0)
(-12,016)
kWh
|
$(-276.0)
-
kW-mo/yr
|
$(-3,335.0)
-
MMBtu
|
$15,100
-
MMBtu
|
|
| 03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $164 | $400 |
$139
9,086
kWh
|
$163
-
kW-mo/yr
|
$(-138.0)
-
MMBtu
|
- | |
| 04 | 2.6121: Reduce hot water temperature to the minimum required | $67 | $30 |
$67
4,689
kWh
|
- | - | - | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $1,996 | $300 |
$842
55,100
kWh
|
$1,154
-
kW-mo/yr
|
- | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,588 | $555 |
$1,588
104,045
kWh
|
- | - | - | |
| 07 | 2.7111: Reduce illumination to minimum necessary levels | $1,479 | $280 |
$586
38,394
kWh
|
$893
-
kW-mo/yr
|
- | - | |
| 08 | 2.7135: Install occupancy sensors | $78 | $200 |
$31
2,052
kWh
|
$47
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $18,601 | $48,865 |
$2,986
195,781
kWh
|
$1,848
-
kW-mo/yr
|
$(-1,333.0)
-
MMBtu
|
$15,100
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs