| Assessment Year | 2000 |
|---|---|
| Principal Product | Fiber Board |
| NAICS |
n/a
|
| SIC | 2631: Paperboard Mills |
| Sales Range | $10 M to 50M |
| # of Employees | 75 |
| Plant Area |
160,000
ft2
|
| Annual Production | 5,000
thousand feet
|
| Production Hrs. Annual | 2,210
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $117,963 | 2,283,998 |
kWh
|
$0.052 |
| Electricity Demand | $19,511 | 6,155 |
kW-mo/yr
|
$3.17 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $6,459 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,882 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4226: Use / purchase optimum sized compressor | $386 | - |
$386
7,620
kWh
|
- | - | - | - | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $587 | $590 |
$179
3,517
kWh
|
$15
-
kW-mo/yr
|
- | $270 | - | $123 | - | |
| 03 | 2.7134: Use photocell controls | $124 | $350 |
$93
1,758
kWh
|
$31
-
kW-mo/yr
|
- | - | - | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $862 | $6,560 |
$649
12,603
kWh
|
$213
-
kW-mo/yr
|
- | - | - | - | - | |
| 05 | 2.2628: Utilize a less expensive cooling method | $913 | - |
$442
8,499
kWh
|
$221
-
kW-mo/yr
|
- | - | $250 | - | - | |
| 06 | 4.425: Eliminate/reduce redundant inspections | $134 | - | - | - | - | $134 | - | - | - | |
| 07 | 2.3511: Use plant owned transformers or lease transformers | $2,211 | $200 | - | - | $(-3,585.0) | - | - | - | $5,796 | |
| 08 | 2.8114: Change rate schedules or other changes in utility service | $1,242 | $250 | - | - | $1,242 | - | - | - | - | |
| TOTAL RECOMMENDED | $6,459 | $7,950 |
$1,749
33,997
kWh
|
$480
-
kW-mo/yr
|
$(-2,343.0) | $404 | $250 | $123 | $5,796 | ||
| TOTAL IMPLEMENTED | $2,882 | $7,150 |
$1,656
32,239
kWh
|
$449
-
kW-mo/yr
|
- | $404 | $250 | $123 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs