Assessment Year | 2015 |
---|---|
Principal Product | Polyurethane Foam-Carpet Padding |
NAICS | 326140: Polystyrene Foam Product Manufacturing |
SIC | 3086: Plastics Foam Products |
Sales Range | $10 M to 50M |
# of Employees | 45 |
Plant Area |
175,000
ft2
|
Annual Production | 32,400,000
lb
|
Production Hrs. Annual | 5,200
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $68,647 | 1,652,936 |
kWh
|
$0.042 |
Electricity Demand | $152,003 | 13,359 |
kW-mo/yr
|
$11.38 |
Natural Gas | $109,087 | 17,343 |
MMBtu
|
$6.29 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $94,360 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,216 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $171 | $294 |
$105
2,532
kWh
|
$66
-
kW-mo/yr
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,045 | $1,800 |
$498
12,000
kWh
|
$546
-
kW-mo/yr
|
- | - | |
03 | 2.7135: Install occupancy sensors | $2,876 | $2,860 |
$1,768
42,578
kWh
|
$1,107
-
kW-mo/yr
|
- | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,305 | $5,750 |
$5,404
130,128
kWh
|
$2,901
-
kW-mo/yr
|
- | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $22,548 | $52,000 |
$13,138
316,338
kWh
|
$9,410
-
kW-mo/yr
|
- | - | |
06 | 2.6212: Turn off equipment during breaks, reduce operating time | $85 | - |
$85
2,052
kWh
|
- | - | - | |
07 | 2.2511: Insulate bare equipment | $1,484 | $603 | - | - |
$1,484
-
MMBtu
|
- | |
08 | 2.4322: Use or replace with energy efficient substitutes | $57,847 | $55,000 | - | - |
$51,446
-
MMBtu
|
$6,401 | |
TOTAL RECOMMENDED | $94,360 | $118,307 |
$20,999
505,628
kWh
|
$14,031
-
kW-mo/yr
|
$52,930
-
MMBtu
|
$6,401 | ||
TOTAL IMPLEMENTED | $1,216 | $2,094 |
$603
14,532
kWh
|
$612
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs