Assessment Year | 1999 |
---|---|
Principal Product | Steel Wire |
NAICS |
n/a
|
SIC | 3315: Steel Wiredrawing and Steel Nails and Spikes |
Sales Range | $5 M to 10M |
# of Employees | 65 |
Plant Area |
200,000
ft2
|
Annual Production | 14,000,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $83,167 | 7,643,904 |
kWh
|
$0.011 |
Electricity Demand | $308,039 | 19,453 |
kW-mo/yr
|
$15.84 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $127,474 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,063 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4151: Develop a repair/replace policy | $22,377 | $60,343 |
$5,972
538,687
kWh
|
$16,405
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 2.7135: Install occupancy sensors | $128 | $200 |
$40
3,517
kWh
|
$88
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $344 | $180 |
$344
31,067
kWh
|
- | - | - | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3 | $300 |
$22
2,052
kWh
|
$44
-
kW-mo/yr
|
- | $(-116.0) | - | $53 | - | |
05 | 2.8121: Apply for tax-free status for energy purchases | $4,719 | $250 | - | - | - | - | $4,719 | - | - | |
06 | 4.425: Eliminate/reduce redundant inspections | $(-177.0) | $336 | - | - | - | - | $(-177.0) | - | - | |
07 | 4.821: Pay bills on time to avoid late fees | $9,218 | $250 | - | - |
$9,218
-
Tgal
|
- | - | - | - | |
08 | 3.4114: Replace city water with recycled water via cooling tower | $90,862 | $120,000 |
$(-344.0)
(-31,067)
kWh
|
$(-946.0)
-
kW-mo/yr
|
- | - | - | - |
$92,152
-
Tgal
|
|
TOTAL RECOMMENDED | $127,474 | $181,859 |
$6,034
544,256
kWh
|
$15,591
-
kW-mo/yr
|
$9,218
-
Tgal
|
$(-116.0) | $4,542 | $53 |
$92,152
-
Tgal
|
||
TOTAL IMPLEMENTED | $5,063 | $430 |
$344
31,067
kWh
|
- | - | - | $4,719 | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs