Assessment Year | 1999 |
---|---|
Principal Product | Coil Winding machines |
NAICS |
n/a
|
SIC | 3559: Special Industry Machinery, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
31,000
ft2
|
Annual Production | 50
pieces
|
Production Hrs. Annual | 2,295
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $26,357 | 532,239 |
kWh
|
$0.050 |
Electricity Demand | $9,889 | 2,317 |
kW-mo/yr
|
$4.27 |
LPG | $5,674 | 903 |
MMBtu
|
$6.28 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $10,910 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $349 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (haz) Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7232: Replace existing hvac unit with high efficiency model | $9,628 | - |
$1,777
36,049
kWh
|
$416
-
kW-mo/yr
|
- | - | $7,435 | |
02 | 2.7124: Make a practice of turning off lights when not needed | $329 | $240 |
$222
4,396
kWh
|
$107
-
kW-mo/yr
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $297 | $40 |
$173
3,517
kWh
|
$79
-
kW-mo/yr
|
- | $45 | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $351 | $510 |
$158
3,224
kWh
|
$19
-
kW-mo/yr
|
- | $174 | - | |
05 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $134 | $500 | - | - |
$134
-
lb
|
- | - | |
06 | 2.3132: Recharge batteries on during off-peak demand periods | $20 | - | - |
$20
-
kW-mo/yr
|
- | - | - | |
07 | 2.4151: Develop a repair/replace policy | $151 | $677 |
$102
2,052
kWh
|
$49
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $10,910 | $1,967 |
$2,432
49,238
kWh
|
$690
-
kW-mo/yr
|
$134
-
lb
|
$219 | $7,435 | ||
TOTAL IMPLEMENTED | $349 | $240 |
$222
4,396
kWh
|
$127
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (haz) Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs