Assessment Year | 2021 |
---|---|
Principal Product | Machined Parts for various applications |
NAICS | 332710: Machine Shops |
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 160 |
Plant Area |
81,500
ft2
|
Annual Production | 1,000,000
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $383,040 | 3,270,186 |
kWh
|
$0.12 |
Electricity Demand | $235,316 | 7,167 |
kW-mo/yr
|
$32.83 |
Electricity Fees | $5,484 | - |
|
- |
Natural Gas | $8,389 | 592 |
MMBtu
|
$14.17 |
TOTAL YEARLY COSTS | $632,229 | |||
RECOMMENDED SAVINGS* | $83,038 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $33,977 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $20,821 | - |
$20,821
185,406
kWh
|
- | - | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,911 | - |
$9,511
84,690
kWh
|
- | $(-1,600.0) | - | - | |
03 | 2.4239: Eliminate or reduce compressed air usage | $9,406 | $3,350 |
$9,406
83,761
kWh
|
- | - | - | - | |
04 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $24,340 | $29,296 |
$24,340
216,750
kWh
|
- | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,660 | $40,195 |
$8,591
76,497
kWh
|
$6,910
-
kW-mo/yr
|
$28 | $1,131 | - | |
06 | 3.5217: Reuse / recycle/ sell paper products | $3,900 | - | - | - | - | - | $3,900 | |
TOTAL RECOMMENDED | $83,038 | $72,841 |
$72,669
647,104
kWh
|
$6,910
-
kW-mo/yr
|
$(-1,572.0) | $1,131 | $3,900 | ||
TOTAL IMPLEMENTED | $33,977 | $43,545 |
$27,508
244,948
kWh
|
$6,910
-
kW-mo/yr
|
$(-1,572.0) | $1,131 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs