Assessment Year | 1999 |
---|---|
Principal Product | Vibration Isolation and Control Devices |
NAICS |
n/a
|
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 263 |
Plant Area |
112,300
ft2
|
Annual Production | 12,700,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $546,398 | 10,055,393 |
kWh
|
$0.054 |
Electricity Demand | $379,385 | 22,110 |
kW-mo/yr
|
$17.16 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $49,149 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $27,626 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.812: Apply for investment incentives | $4,400 | $250 | - | - | - | - | - | $4,400 | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $358 | $560 |
$52
4,689
kWh
|
$119
-
kW-mo/yr
|
- | - | - | - | $187 | - | |
03 | 4.222: Purchase re-conditioned material instead of new | $22,061 | $57,704 |
$5,369
482,708
kWh
|
$12,280
-
kW-mo/yr
|
- | - | - | - | - | $4,412 | |
04 | 2.3134: Shift from daytime to nighttime operation | $3,512 | $500 | - |
$3,512
-
kW-mo/yr
|
- | - | - | - | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $962 | $1,000 |
$449
40,445
kWh
|
$513
-
kW-mo/yr
|
- | - | - | - | - | - | |
06 | 2.3212: Optimize plant power factor | $13,400 | $6,000 | - | - | $13,400 | - | - | - | - | - | |
07 | 2.8114: Change rate schedules or other changes in utility service | $1,416 | $250 | - | - | $1,416 | - | - | - | - | - | |
08 | 2.2514: Cover open tanks | $486 | $450 |
$148
13,189
kWh
|
$338
-
kW-mo/yr
|
- | - | - | - | - | - | |
09 | 2.6218: Turn off equipment when not in use | $319 | $143 |
$31
2,931
kWh
|
$288
-
kW-mo/yr
|
- | - | - | - | - | - | |
10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $807 | $200 |
$807
72,685
kWh
|
- | - | - | - | - | - | - | |
11 | 3.5113: Sell oil to recycler | $900 | $2,000 | - | - | - |
$900
-
gal
|
- | - | - | - | |
12 | 4.611: Begin a practice of predictive / preventative maintenance | $528 | - | - | - | - | - | $528 | - | - | - | |
TOTAL RECOMMENDED | $49,149 | $69,057 |
$6,856
616,647
kWh
|
$17,050
-
kW-mo/yr
|
$14,816 |
$900
-
gal
|
$528 | $4,400 | $187 | $4,412 | ||
TOTAL IMPLEMENTED | $27,626 | $58,714 |
$6,228
560,082
kWh
|
$12,399
-
kW-mo/yr
|
- | - | - | $4,400 | $187 | $4,412 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs