ITAC Assessment: ND0334
ITAC logo
ITAC Assessment: ND0334
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Vibration Isolation and Control Devices
NAICS
n/a
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 263
Plant Area 112,300
ft2
Annual Production 12,700,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $546,398 10,055,393
kWh
Electricity Demand $379,385 22,110
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $49,149 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $27,626

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Other Liquid (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 4.812: Apply for investment incentives $4,400 $250 - - - - - $4,400 - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $358 $560 $52
4,689
kWh
$119
-
kW-mo/yr
- - - - $187 -
03 4.222: Purchase re-conditioned material instead of new $22,061 $57,704 $5,369
482,708
kWh
$12,280
-
kW-mo/yr
- - - - - $4,412
04 2.3134: Shift from daytime to nighttime operation $3,512 $500 - $3,512
-
kW-mo/yr
- - - - - -
05 2.4221: Install compressor air intakes in coolest locations $962 $1,000 $449
40,445
kWh
$513
-
kW-mo/yr
- - - - - -
06 2.3212: Optimize plant power factor $13,400 $6,000 - - $13,400 - - - - -
07 2.8114: Change rate schedules or other changes in utility service $1,416 $250 - - $1,416 - - - - -
08 2.2514: Cover open tanks $486 $450 $148
13,189
kWh
$338
-
kW-mo/yr
- - - - - -
09 2.6218: Turn off equipment when not in use $319 $143 $31
2,931
kWh
$288
-
kW-mo/yr
- - - - - -
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $807 $200 $807
72,685
kWh
- - - - - - -
11 3.5113: Sell oil to recycler $900 $2,000 - - - $900
-
gal
- - - -
12 4.611: Begin a practice of predictive / preventative maintenance $528 - - - - - $528 - - -
TOTAL RECOMMENDED $49,149 $69,057 $6,856
616,647
kWh
$17,050
-
kW-mo/yr
$14,816 $900
-
gal
$528 $4,400 $187 $4,412
TOTAL IMPLEMENTED $27,626 $58,714 $6,228
560,082
kWh
$12,399
-
kW-mo/yr
- - - $4,400 $187 $4,412
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Other Liquid (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs