ITAC Assessment: ND0330
ITAC logo
ITAC Assessment: ND0330
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Insulated Metal Doors
NAICS
n/a
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $10
M
to 50
M
# of Employees 113
Plant Area 85,000
ft2
Annual Production 700,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $58,905 1,955,451
kWh
Electricity Demand $53,290 4,885
kW-mo/yr
Electricity Fees $5,873 -
Natural Gas $62,791 13,228
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $27,421 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $22,369

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,347 $200 $1,347
44,842
kWh
- - - - - - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $228 $320 $81
2,638
kWh
$40
-
kW-mo/yr
- - - - - $107 -
03 2.2211: Use optimum temperature $15 $10 $15
586
kWh
- - - - - - - -
04 2.2511: Insulate bare equipment $3,950 $3,800 - - - $3,950
-
MMBtu
- - - - -
05 2.4221: Install compressor air intakes in coolest locations $1,337 $1,000 $992
32,825
kWh
$345
-
kW-mo/yr
- - - - - - -
06 2.3212: Optimize plant power factor $5,430 $4,252 - - $5,430 - - - - - -
07 2.1311: Replace electrically-operated equipment with fossil fuel equipment $131 $350 $65
2,052
kWh
$108
-
kW-mo/yr
- $(-42.0)
-
MMBtu
- - - - -
08 3.7214: Reduce or eliminate waste $1,067 $95 - - - - $200
-
lb
$867 - - -
09 3.4151: Minimize water usage $821 $960 - - - - - - - - $821
-
Tgal
10 4.222: Purchase re-conditioned material instead of new $3,873 $17,271 $2,283
75,909
kWh
$1,590
-
kW-mo/yr
- - - - - - -
11 2.4314: Use synthetic lubricant $3,469 $1,375 $1,980
65,651
kWh
$1,379
-
kW-mo/yr
- - - - - $110 -
12 2.4226: Use / purchase optimum sized compressor $2,763 $750 $2,763
91,735
kWh
- - - - - - - -
13 4.811: Demolish old building to reduce tax and insurance bills $2,990 $250 - - - - - - $2,990 - -
TOTAL RECOMMENDED $27,421 $30,633 $9,526
316,238
kWh
$3,462
-
kW-mo/yr
$5,430 $3,908
-
MMBtu
$200
-
lb
$867 $2,990 $217 $821
-
Tgal
TOTAL IMPLEMENTED $22,369 $27,573 $5,706
189,626
kWh
$3,009
-
kW-mo/yr
$5,430 $3,950
-
MMBtu
$200
-
lb
$867 $2,990 $217 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs