Assessment Year | 1999 |
---|---|
Principal Product | Fire Fighting Nozzles |
NAICS |
n/a
|
SIC | 3569: General Industrial Machinery and Equipment, Not Elsewhere |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
80,000
ft2
|
Annual Production | 2,500
pieces
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $83,953 | 1,331,770 |
kWh
|
$0.063 |
Electricity Demand | $31,363 | 3,828 |
kW-mo/yr
|
$8.19 |
Natural Gas | $4,061 | 718 |
MMBtu
|
$5.66 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $48,868 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $40,768 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.521: Clear and rent existing space | $40,000 | $18,000 | - | - | - | - | - | $40,000 | - | |
02 | 2.4133: Use most efficient type of electric motors | $720 | $7,006 |
$621
5,862
kWh
|
$99
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.4226: Use / purchase optimum sized compressor | $2,442 | $5,000 |
$2,442
44,549
kWh
|
- | - | - | - | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $1,236 | $1,500 |
$1,236
21,981
kWh
|
- | - | - | - | - | - | |
05 | 2.7111: Reduce illumination to minimum necessary levels | $1,296 | $300 |
$898
16,413
kWh
|
$398
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 3.4151: Minimize water usage | $870 | $1,400 | - | - | - |
$870
-
Tgal
|
- | - | - | |
07 | 3.4151: Minimize water usage | $878 | $2,300 | - | - | - |
$755
-
Tgal
|
$200 | - | $(-77.0) | |
08 | 4.811: Demolish old building to reduce tax and insurance bills | $658 | $250 | - | - | $658 | - | - | - | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $587 | $100 |
$587
10,844
kWh
|
- | - | - | - | - | - | |
10 | 4.611: Begin a practice of predictive / preventative maintenance | $181 | $390 | - | - | - | - | $181 | - | - | |
TOTAL RECOMMENDED | $48,868 | $36,246 |
$5,784
99,649
kWh
|
$497
-
kW-mo/yr
|
$658 |
$1,625
-
Tgal
|
$381 | $40,000 | $(-77.0) | ||
TOTAL IMPLEMENTED | $40,768 | $18,490 |
$587
10,844
kWh
|
- | - | - | $181 | $40,000 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs