Assessment Year | 1999 |
---|---|
Principal Product | Electric Transformers |
NAICS |
n/a
|
SIC | 3612: Power, Distribution, and Specialty Transformers |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
54,000
ft2
|
Annual Production | 6,000,000
pieces
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $36,442 | 2,218,933 |
kWh
|
$0.016 |
Electricity Demand | $58,179 | 5,331 |
kW-mo/yr
|
$10.91 |
Natural Gas | $25,016 | 4,113 |
MMBtu
|
$6.08 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $9,158 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,420 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $641 | $1,000 |
$233
13,775
kWh
|
$408
-
kW-mo/yr
|
- | - | - | |
02 | 2.1135: Repair furnaces and oven doors so that they seal efficiently | $232 | $130 | - | - |
$232
-
MMBtu
|
- | - | |
03 | 2.4226: Use / purchase optimum sized compressor | $6,626 | $10,000 |
$2,412
142,145
kWh
|
$4,214
-
kW-mo/yr
|
- | - | - | |
04 | 2.7144: Install spectral reflectors / delamp | $97 | $80 |
$35
2,052
kWh
|
$62
-
kW-mo/yr
|
- | - | - | |
05 | 2.7124: Make a practice of turning off lights when not needed | $299 | $190 |
$109
6,448
kWh
|
$190
-
kW-mo/yr
|
- | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $248 | $80 |
$248
14,654
kWh
|
- | - | - | - | |
07 | 3.5316: Contract a wood pallet recycling company | $720 | $20 | - | - | - |
$720
-
lb
|
- | |
08 | 4.821: Pay bills on time to avoid late fees | $295 | - | - | - | - | - | $295 | |
TOTAL RECOMMENDED | $9,158 | $11,500 |
$3,037
179,074
kWh
|
$4,874
-
kW-mo/yr
|
$232
-
MMBtu
|
$720
-
lb
|
$295 | ||
TOTAL IMPLEMENTED | $8,420 | $10,420 |
$2,769
163,247
kWh
|
$4,404
-
kW-mo/yr
|
$232
-
MMBtu
|
$720
-
lb
|
$295 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs