Assessment Year | 1999 |
---|---|
Principal Product | Teflon Products |
NAICS |
n/a
|
SIC | 3083: Laminated Plastics Plate, Sheet, and Profile Shapes |
Sales Range | $5 M to 10M |
# of Employees | 50 |
Plant Area |
28,000
ft2
|
Annual Production | 100,000,000
pieces
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Demand | $38,122 | 4,506 |
kW-mo/yr
|
$8.46 |
Electricity Fees | $5,978 | - |
|
- |
Natural Gas | $4,972 | 870 |
MMBtu
|
$5.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,537 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,925 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (haz) Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $7,589 | $40,800 |
$14,449
440,797
kWh
|
$3,022
-
kW-mo/yr
|
- |
$(-9,882.0)
-
MMBtu
|
- | - | - | |
02 | 4.811: Demolish old building to reduce tax and insurance bills | $3,731 | $250 | - | - | $3,731 | - | - | - | - | |
03 | 4.821: Pay bills on time to avoid late fees | $2,584 | - | - | - | $2,451 |
$133
-
MMBtu
|
- | - | - | |
04 | 4.222: Purchase re-conditioned material instead of new | $546 | $991 |
$297
9,086
kWh
|
$181
-
kW-mo/yr
|
- | - | - | - | $68 | |
05 | 2.4226: Use / purchase optimum sized compressor | $1,064 | $500 |
$1,064
32,532
kWh
|
- | - | - | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $736 | $1,746 |
$403
12,309
kWh
|
$333
-
kW-mo/yr
|
- | - | - | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $670 | $140 |
$427
12,896
kWh
|
$243
-
kW-mo/yr
|
- | - | - | - | - | |
08 | 2.7135: Install occupancy sensors | $256 | $600 |
$163
4,982
kWh
|
$93
-
kW-mo/yr
|
- | - | - | - | - | |
09 | 3.8211: Convert to aqueous cleaning system | $114 | $100 | - | - | - | - |
$114
-
gal
|
- | - | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $109 | $360 |
$40
1,172
kWh
|
$16
-
kW-mo/yr
|
- | - | - | $53 | - | |
11 | 2.4221: Install compressor air intakes in coolest locations | $106 | $200 |
$106
3,224
kWh
|
- | - | - | - | - | - | |
12 | 2.2211: Use optimum temperature | $32 | $10 | - | - | - |
$32
-
MMBtu
|
- | - | - | |
TOTAL RECOMMENDED | $17,537 | $45,697 |
$16,949
516,998
kWh
|
$3,888
-
kW-mo/yr
|
$6,182 |
$(-9,717.0)
-
MMBtu
|
$114
-
gal
|
$53 | $68 | ||
TOTAL IMPLEMENTED | $7,925 | $2,191 |
$993
30,188
kWh
|
$517
-
kW-mo/yr
|
$6,182 |
$165
-
MMBtu
|
- | - | $68 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (haz) Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs