ITAC Assessment: ND0318
ITAC logo
ITAC Assessment: ND0318
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Steering Columns
NAICS
n/a
SIC 3400:
Sales Range $10
M
to 50
M
# of Employees 279
Plant Area 122,650
ft2
Annual Production 560,000
pieces
Production Hrs. Annual 4,250
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $131,239 3,888,042
kWh
Electricity Demand $82,523 8,661
kW-mo/yr
Electricity Fees $12,073 -
Natural Gas $63,375 13,320
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $27,779 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $280

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Other Liquid (haz) Savings Personnel Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.7232: Replace existing hvac unit with high efficiency model $18,857 $13,000 $(-3,204.0)
(-94,959)
kWh
$(-1,449.0)
-
kW-mo/yr
- $16,760
-
MMBtu
- - $6,750 - -
02 2.3212: Optimize plant power factor $1,297 $5,040 - - $1,297 - - - - - -
03 3.4111: Use closed cycle process to minimize waste water production $1,026 $600 - - - - $1,026
-
Tgal
- - - -
04 4.222: Purchase re-conditioned material instead of new $1,536 $4,647 $1,024
18,757
kWh
$248
-
kW-mo/yr
- - - - - - $264
05 3.4151: Minimize water usage $1,227 $5,750 - - - - $967
-
Tgal
- $500 $(-240.0) -
06 3.8211: Convert to aqueous cleaning system $662 $200 - - - - - $662
-
gal
- - -
07 2.4221: Install compressor air intakes in coolest locations $1,043 $600 $895
26,377
kWh
$148
-
kW-mo/yr
- - - - - - -
08 2.1311: Replace electrically-operated equipment with fossil fuel equipment $546 $2,370 $866
25,791
kWh
$201
-
kW-mo/yr
- $(-521.0)
-
MMBtu
- - - - -
09 2.2514: Cover open tanks $347 $200 - - - $347
-
MMBtu
- - - - -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $360 $550 $124
3,810
kWh
$41
-
kW-mo/yr
- - - - - $195 -
11 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $280 $180 $280
4,982
kWh
- - - - - - - -
12 2.4111: Utilize energy-efficient belts and other improved mechanisms $483 $240 $269
7,913
kWh
$214
-
kW-mo/yr
- - - - - - -
13 2.7122: Disconnect ballasts $115 $230 $74
2,052
kWh
$41
-
kW-mo/yr
- - - - - - -
TOTAL RECOMMENDED $27,779 $33,607 $328
(-5,277)
kWh
$(-556.0)
-
kW-mo/yr
$1,297 $16,586
-
MMBtu
$1,993
-
Tgal
$662
-
gal
$7,250 $(-45.0) $264
TOTAL IMPLEMENTED $280 $180 $280
4,982
kWh
- - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Other Liquid (haz) Savings Personnel Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs