Assessment Year | 1998 |
---|---|
Principal Product | Trophies |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 170 |
Plant Area |
100,000
ft2
|
Annual Production | 20,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $214,337 | 4,008,793 |
kWh
|
$0.053 |
Electricity Demand | $82,578 | 8,581 |
kW-mo/yr
|
$9.62 |
Natural Gas | $55,600 | 11,431 |
MMBtu
|
$4.86 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $42,263 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,799 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $17,390 | $46,000 |
$(-3,823.0)
(-71,512)
kWh
|
$(-1,376.0)
-
kW-mo/yr
|
- |
$22,589
-
MMBtu
|
- | - | - | - | |
02 | 2.7229: Air condition only space necessary | $8,600 | $37,000 |
$8,600
160,903
kWh
|
- | - | - | - | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $602 | $80 |
$602
11,137
kWh
|
- | - | - | - | - | - | - | |
04 | 4.821: Pay bills on time to avoid late fees | $4,665 | - | - | - | $4,665 | - | - | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,167 | $9,920 |
$2,329
43,669
kWh
|
$838
-
kW-mo/yr
|
- | - | - | - | - | - | |
06 | 4.811: Demolish old building to reduce tax and insurance bills | $2,075 | $250 | - | - | - | - | - | - | $2,075 | - | |
07 | 2.2437: Recover waste heat from equipment | $1,405 | $250 | - | - | - |
$1,405
-
MMBtu
|
- | - | - | - | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,335 | $600 |
$982
18,464
kWh
|
$353
-
kW-mo/yr
|
- | - | - | - | - | - | |
09 | 2.7124: Make a practice of turning off lights when not needed | $794 | $150 |
$558
10,551
kWh
|
$236
-
kW-mo/yr
|
- | - | - | - | - | - | |
10 | 2.4221: Install compressor air intakes in coolest locations | $617 | $363 |
$617
11,430
kWh
|
- | - | - | - | - | - | - | |
11 | 2.7135: Install occupancy sensors | $485 | $400 |
$485
9,086
kWh
|
- | - | - | - | - | - | - | |
12 | 3.8211: Convert to aqueous cleaning system | $393 | $200 | - | - | - | - |
$393
-
gal
|
- | - | - | |
13 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $342 | $550 |
$132
2,345
kWh
|
$33
-
kW-mo/yr
|
- | - | - | - | - | $177 | |
14 | 3.5316: Contract a wood pallet recycling company | $393 | $60 | - | - | - | - | - |
$393
-
lb
|
- | - | |
TOTAL RECOMMENDED | $42,263 | $95,823 |
$10,482
196,073
kWh
|
$84
-
kW-mo/yr
|
$4,665 |
$23,994
-
MMBtu
|
$393
-
gal
|
$393
-
lb
|
$2,075 | $177 | ||
TOTAL IMPLEMENTED | $8,799 | $1,453 |
$2,759
51,582
kWh
|
$589
-
kW-mo/yr
|
$4,665 | - |
$393
-
gal
|
$393
-
lb
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs