ITAC Assessment: ND0316
ITAC logo
ITAC Assessment: ND0316
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Trophies
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 170
Plant Area 100,000
ft2
Annual Production 20,000,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $214,337 4,008,793
kWh
Electricity Demand $82,578 8,581
kW-mo/yr
Natural Gas $55,600 11,431
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $42,263 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,799

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.2414: Use waste heat from hot flue gases to preheat $17,390 $46,000 $(-3,823.0)
(-71,512)
kWh
$(-1,376.0)
-
kW-mo/yr
- $22,589
-
MMBtu
- - - -
02 2.7229: Air condition only space necessary $8,600 $37,000 $8,600
160,903
kWh
- - - - - - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $602 $80 $602
11,137
kWh
- - - - - - -
04 4.821: Pay bills on time to avoid late fees $4,665 - - - $4,665 - - - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $3,167 $9,920 $2,329
43,669
kWh
$838
-
kW-mo/yr
- - - - - -
06 4.811: Demolish old building to reduce tax and insurance bills $2,075 $250 - - - - - - $2,075 -
07 2.2437: Recover waste heat from equipment $1,405 $250 - - - $1,405
-
MMBtu
- - - -
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,335 $600 $982
18,464
kWh
$353
-
kW-mo/yr
- - - - - -
09 2.7124: Make a practice of turning off lights when not needed $794 $150 $558
10,551
kWh
$236
-
kW-mo/yr
- - - - - -
10 2.4221: Install compressor air intakes in coolest locations $617 $363 $617
11,430
kWh
- - - - - - -
11 2.7135: Install occupancy sensors $485 $400 $485
9,086
kWh
- - - - - - -
12 3.8211: Convert to aqueous cleaning system $393 $200 - - - - $393
-
gal
- - -
13 2.7142: Utilize higher efficiency lamps and/or ballasts $342 $550 $132
2,345
kWh
$33
-
kW-mo/yr
- - - - - $177
14 3.5316: Contract a wood pallet recycling company $393 $60 - - - - - $393
-
lb
- -
TOTAL RECOMMENDED $42,263 $95,823 $10,482
196,073
kWh
$84
-
kW-mo/yr
$4,665 $23,994
-
MMBtu
$393
-
gal
$393
-
lb
$2,075 $177
TOTAL IMPLEMENTED $8,799 $1,453 $2,759
51,582
kWh
$589
-
kW-mo/yr
$4,665 - $393
-
gal
$393
-
lb
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs