ITAC Assessment: ND0305
ITAC logo
ITAC Assessment: ND0305
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Commercial Refrigerators
NAICS
n/a
SIC 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment
Sales Range $50
M
to 100
M
# of Employees 250
Plant Area 400,000
ft2
Annual Production 13,000
pieces
Production Hrs. Annual 8,400
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $155,750 7,457,796
kWh
Electricity Demand $181,414 15,646
kW-mo/yr
Electricity Fees $13,262 -
Natural Gas $282,219 81,883
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $121,110 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $43,583

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Primary Product Savings
01 2.7491: Insulate glazing, walls, ceilings, and roofs $6,973 $22,500 - - - $6,973
-
MMBtu
- - - - - -
02 2.3212: Optimize plant power factor $19,450 $11,886 - $19,450
-
kW-mo/yr
- - - - - - - -
03 4.652: Replace existing equipment with more suitable substitutes $40,120 $85,000 - - - - - - - $34,120 $1,500 $4,500
04 4.711: Initiate a total quality management program $13,776 $4,000 - $13,776
-
kW-mo/yr
- - - - - - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $12,160 $49,023 $7,063
245,897
kWh
$5,097
-
kW-mo/yr
- - - - - - - -
06 2.4226: Use / purchase optimum sized compressor $5,626 $9,836 $5,626
361,665
kWh
- - - - - - - - -
07 4.513: Re-arrange equipment layout to reduce labor costs $4,306 $3,240 $(-211.0)
(-13,482)
kWh
$(-683.0)
-
kW-mo/yr
- - - - - $5,200 - -
08 3.4111: Use closed cycle process to minimize waste water production $3,722 $10,000 $(-664.0)
(-14,947)
kWh
- - - $4,386
-
Tgal
- - - - -
09 2.3212: Optimize plant power factor $5,272 $1,250 - $(-485.0)
-
kW-mo/yr
$5,757 - - - - - - -
10 2.4133: Use most efficient type of electric motors $3,611 $15,801 $1,631
104,924
kWh
$1,980
-
kW-mo/yr
- - - - - - - -
11 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,422 $340 $1,422
91,442
kWh
- - - - - - - - -
12 2.2437: Recover waste heat from equipment $1,101 $5,400 - - - $1,101
-
MMBtu
- - - - - -
13 3.8211: Convert to aqueous cleaning system $793 $150 - - - - - $793
-
gal
- - - -
14 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,100 $1,180 $498
31,946
kWh
$602
-
kW-mo/yr
- - - - - - - -
15 2.4321: Upgrade obsolete equipment $670 $1,750 $992
22,274
kWh
- - $(-322.0)
-
MMBtu
- - - - - -
16 3.5315: Lease / purchase baler; sell cardboard to recycler $501 $2,800 - - - - - - $501
-
lb
- - -
17 3.5313: Increase amount of waste recovered for resale $312 $50 - - - - - - $312
-
lb
- - -
18 2.6218: Turn off equipment when not in use $128 $275 $128
8,206
kWh
- - - - - - - - -
19 2.4231: Reduce the pressure of compressed air to the minimum required $67 $20 $67
4,396
kWh
- - - - - - - - -
TOTAL RECOMMENDED $121,110 $224,501 $16,552
842,321
kWh
$39,737
-
kW-mo/yr
$5,757 $7,752
-
MMBtu
$4,386
-
Tgal
$793
-
gal
$813
-
lb
$39,320 $1,500 $4,500
TOTAL IMPLEMENTED $43,583 $89,645 $2,048
131,594
kWh
$602
-
kW-mo/yr
- - - - $813
-
lb
$34,120 $1,500 $4,500
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs