ITAC Assessment: ND0275
ITAC logo
ITAC Assessment: ND0275
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product pallet racks
NAICS
n/a
SIC 3429: Hardware, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 220
Plant Area 300,000
ft2
Annual Production 35,000
ton
Production Hrs. Annual 4,250
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $269,187 7,211,606
kWh
Electricity Demand $188,537 19,343
kW-mo/yr
Natural Gas $466,073 97,042
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,552,297 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $231,660

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 4.212: Adopt in-house material generation $1,307,600 $1,300,000 - - - - $1,307,600 -
02 4.322: Eliminate old stock and modify inventory control $217,807 $100,000 $10,471
280,481
kWh
$7,336
-
kW-mo/yr
- $200,000 - -
03 2.4133: Use most efficient type of electric motors $2,561 $1,435 $1,505
43,962
kWh
$1,056
-
kW-mo/yr
- - - -
04 2.3212: Optimize plant power factor $7,023 $15,339 - - - - $7,023 -
05 2.4226: Use / purchase optimum sized compressor $6,117 $4,500 $6,117
180,832
kWh
- - - - -
06 2.2437: Recover waste heat from equipment $5,175 $993 - - $5,175
-
MMBtu
- - -
07 2.4221: Install compressor air intakes in coolest locations $2,266 $400 $2,266
35,756
kWh
- - - - -
08 4.114: Add/modify equipment to improve drying process $1,310 $330 - - - $1,310 - -
09 2.7135: Install occupancy sensors $652 $600 $652
19,050
kWh
- - - - -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $324 $363 $191
4,982
kWh
$133
-
kW-mo/yr
- - - -
11 2.7124: Make a practice of turning off lights when not needed $276 - $162
4,396
kWh
$114
-
kW-mo/yr
- - - -
12 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $149 $60 $149
4,396
kWh
- - - - -
13 2.6218: Turn off equipment when not in use $55 - $55
1,465
kWh
- - - - -
14 4.821: Pay bills on time to avoid late fees $3 - - - - $3 - -
15 3.7137: Replace cloth rags with paper towels $528 $450 - - - - - $528
16 3.5316: Contract a wood pallet recycling company $360 - - - - - - $360
17 3.8132: Use less toxic and volatile solvent substitutes $91 $50 - - - - - $91
TOTAL RECOMMENDED $1,552,297 $1,424,520 $21,568
575,320
kWh
$8,639
-
kW-mo/yr
$5,175
-
MMBtu
$201,313 $1,314,623 $979
TOTAL IMPLEMENTED $231,660 $106,928 $18,093
505,275
kWh
$8,392
-
kW-mo/yr
$5,175
-
MMBtu
$200,000 - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs