Assessment Year | 1996 |
---|---|
Principal Product | Heating wire and elements |
NAICS |
n/a
|
SIC | 3643: Current-Carrying Wiring Devices |
Sales Range | $1 M to 5M |
# of Employees | 250 |
Plant Area |
45,000
ft2
|
Annual Production | 37,000
thousand feet
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $86,275 | 1,458,675 |
kWh
|
$0.059 |
Electricity Demand | $37,558 | 3,470 |
kW-mo/yr
|
$10.82 |
Electricity Fees | $(-13,232.0) | - |
|
- |
Natural Gas | $27,076 | 7,618 |
MMBtu
|
$3.55 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $12,227 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,145 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,980 | $719 |
$1,435
32,532
kWh
|
$545
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $315 | $690 |
$269
4,396
kWh
|
$46
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.8112: Combine utility meters | $5,363 | $2,500 | - | - | $5,363 | - | - | - | |
04 | 2.3212: Optimize plant power factor | $474 | $3,612 | - | - | $474 | - | - | - | |
05 | 2.6218: Turn off equipment when not in use | $226 | $70 |
$226
3,517
kWh
|
- | - | - | - | - | |
06 | 2.4133: Use most efficient type of electric motors | $860 | $5,940 |
$698
11,430
kWh
|
$162
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.7135: Install occupancy sensors | $932 | $1,400 |
$932
12,309
kWh
|
- | - | - | - | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $200 | $100 |
$200
3,224
kWh
|
- | - | - | - | - | |
09 | 2.4221: Install compressor air intakes in coolest locations | $504 | $100 |
$504
8,792
kWh
|
- | - | - | - | - | |
10 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $18 | $1,000 |
$25
293
kWh
|
- | - |
$(-7.0)
-
MMBtu
|
- | - | |
11 | 3.5311: Recover and reuse waste material | $1,355 | $700 | - | - | - | - |
$3
-
lb
|
$1,352 | |
TOTAL RECOMMENDED | $12,227 | $16,831 |
$4,289
76,493
kWh
|
$753
-
kW-mo/yr
|
$5,837 |
$(-7.0)
-
MMBtu
|
$3
-
lb
|
$1,352 | ||
TOTAL IMPLEMENTED | $3,145 | $6,910 |
$1,628
26,963
kWh
|
$162
-
kW-mo/yr
|
- | - |
$3
-
lb
|
$1,352 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs