ITAC Assessment: ND0238
ITAC logo
ITAC Assessment: ND0238
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Coil Springs
NAICS
n/a
SIC 3490:
Sales Range $10
M
to 50
M
# of Employees 140
Plant Area 84,000
ft2
Annual Production 37,302,194
pieces
Production Hrs. Annual 2,423
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $100,203 1,751,465
kWh
Electricity Demand $58,656 6,410
kW-mo/yr
Electricity Fees $(-18,747.0) -
Natural Gas $40,217 9,693
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,726 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,628

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,350 $480 $3,350
58,030
kWh
- - - -
02 2.4133: Use most efficient type of electric motors $9,194 $14,890 $5,472
93,787
kWh
$3,722
-
kW-mo/yr
- - -
03 2.2437: Recover waste heat from equipment $779 $1,000 - - - $779
-
MMBtu
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,675 $807 $1,091
19,343
kWh
$584
-
kW-mo/yr
- - -
05 2.3212: Optimize plant power factor $934 $1,914 - - $934 - -
06 2.4221: Install compressor air intakes in coolest locations $561 $300 $561
9,086
kWh
- - - -
07 2.7135: Install occupancy sensors $705 $400 $447
7,913
kWh
$258
-
kW-mo/yr
- - -
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $866 $20 $466
7,620
kWh
$400
-
kW-mo/yr
- - -
09 2.8123: Pay utility bills on time $464 - - - $464 - -
10 3.1175: Use a different or recycled raw material $1,198 $1,080 - - - - $1,198
-
lb
TOTAL RECOMMENDED $19,726 $20,891 $11,387
195,779
kWh
$4,964
-
kW-mo/yr
$1,398 $779
-
MMBtu
$1,198
-
lb
TOTAL IMPLEMENTED $12,628 $17,077 $7,124
122,216
kWh
$4,306
-
kW-mo/yr
- - $1,198
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs