| Assessment Year | 1995 |
|---|---|
| Principal Product | Paper Hand Towels |
| NAICS |
n/a
|
| SIC | 2621: Paper Mills |
| Sales Range | $10 M to 50M |
| # of Employees | 77 |
| Plant Area |
131,000
ft2
|
| Annual Production | 30,000
ton
|
| Production Hrs. Annual | 8,700
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,398,364 | 21,150,352 |
kWh
|
$0.066 |
| Natural Gas | $628,053 | 276,184 |
MMBtu
|
$2.27 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $517,141 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $470,987 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,195 | $529 |
$1,195
19,637
kWh
|
- | |
| 02 | 2.4133: Use most efficient type of electric motors | $55,146 | $30,640 |
$55,146
905,334
kWh
|
- | |
| 03 | 2.6218: Turn off equipment when not in use | $135 | - |
$135
2,345
kWh
|
- | |
| 04 | 2.3212: Optimize plant power factor | $28,611 | $49,230 |
$28,611
-
kWh
|
- | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $1,805 | $600 |
$1,805
29,601
kWh
|
- | |
| 06 | 3.4111: Use closed cycle process to minimize waste water production | $399,646 | $125,000 | - |
$399,646
-
Tgal
|
|
| 07 | 3.4131: Minimize contamination of water before treatment | $15,000 | $30,000 | - |
$15,000
-
Tgal
|
|
| 08 | 3.4154: Eliminate leaks in water lines and valves | $4,059 | $1,500 | - |
$4,059
-
Tgal
|
|
| 09 | 3.4154: Eliminate leaks in water lines and valves | $11,544 | $5,800 | - |
$11,544
-
Tgal
|
|
| TOTAL RECOMMENDED | $517,141 | $243,299 |
$86,892
956,917
kWh
|
$430,249
-
Tgal
|
||
| TOTAL IMPLEMENTED | $470,987 | $186,169 |
$56,341
924,971
kWh
|
$414,646
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Water Disposal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs