| Assessment Year | 1995 |
|---|---|
| Principal Product | Hard Chrome Plated Rolls |
| NAICS |
n/a
|
| SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
| Sales Range | $1 M to 5M |
| # of Employees | 42 |
| Plant Area |
45,000
ft2
|
| Annual Production | 21,600
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $214,879 | 2,640,680 |
kWh
|
$0.081 |
| Natural Gas | $20,282 | 4,454 |
MMBtu
|
$4.55 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $40,178 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $37,106 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $2,453 | $2,830 |
$2,453
30,188
kWh
|
- | - | - | |
| 02 | 2.2311: Heat treat parts only to required specifications or standards | $1,082 | $500 |
$1,082
13,189
kWh
|
- | - | - | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $772 | $150 |
$772
9,379
kWh
|
- | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $619 | $459 |
$619
7,620
kWh
|
- | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $201 | $250 |
$201
2,345
kWh
|
- | - | - | |
| 06 | 2.6218: Turn off equipment when not in use | $101 | - |
$101
1,172
kWh
|
- | - | - | |
| 07 | 3.4113: Treat and reuse rinse waters | $27,000 | $45,000 | - |
$27,000
-
Tgal
|
- | - | |
| 08 | 3.4156: Use flow control valves on equipment to optimize water use | $7,300 | $400 | - | - |
$7,300
-
gal
|
- | |
| 09 | 3.6111: Use alternative flocculent to minimize sludge volume | $650 | $3,500 | - | - | - |
$650
-
gal
|
|
| TOTAL RECOMMENDED | $40,178 | $53,089 |
$5,228
63,893
kWh
|
$27,000
-
Tgal
|
$7,300
-
gal
|
$650
-
gal
|
||
| TOTAL IMPLEMENTED | $37,106 | $49,800 |
$2,156
26,085
kWh
|
$27,000
-
Tgal
|
$7,300
-
gal
|
$650
-
gal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs