ITAC Assessment: NC0156
ITAC logo
ITAC Assessment: NC0156
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product bath and kitchen faucets
NAICS
n/a
SIC 3432: Plumbing Fixture Fittings and Trim
Sales Range $50
M
to 100
M
# of Employees 400
Plant Area 280,000
ft2
Annual Production 11,000,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $986,707 30,266,706
kWh
Electricity Demand $611,763 54,379
kW-mo/yr
Electricity Fees $17,938 -
Natural Gas $180,409 45,410
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $564,527 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $526,046

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings Increase in Production Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $9,453 $15,000 $9,713
298,066
kWh
$4,590
-
kW-mo/yr
$(-4,850.0)
-
MMBtu
- - -
02 2.2511: Insulate bare equipment $27,013 $1,295 $25,798
791,325
kWh
$1,215
-
kW-mo/yr
- - - -
03 2.7232: Replace existing hvac unit with high efficiency model $461,046 $1,000,000 $185,996
5,705,451
kWh
$161,257
-
kW-mo/yr
$(-56,207.0)
-
MMBtu
- $170,000 -
04 2.7313: Recycle air for heating, ventilation and air conditioning $65,000 $80,000 $32,625
1,000,879
kWh
$30,375
-
kW-mo/yr
- - $(-4,000.0) $6,000
05 3.1221: Use reactive rinsing $2,015 $325 - - - $2,015
-
Tgal
- -
TOTAL RECOMMENDED $564,527 $1,096,620 $254,132
7,795,721
kWh
$197,437
-
kW-mo/yr
$(-61,057.0)
-
MMBtu
$2,015
-
Tgal
$166,000 $6,000
TOTAL IMPLEMENTED $526,046 $1,080,000 $218,621
6,706,330
kWh
$191,632
-
kW-mo/yr
$(-56,207.0)
-
MMBtu
- $166,000 $6,000
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs