| Assessment Year | 1995 |
|---|---|
| Principal Product | Steel Coil Coating |
| NAICS |
n/a
|
| SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
| Sales Range | $50 M to 100M |
| # of Employees | 240 |
| Plant Area |
100,000
ft2
|
| Annual Production | 350,000
ton
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,709,461 | 27,785,757 |
kWh
|
$0.062 |
| Natural Gas | $1,971,107 | 889,617 |
MMBtu
|
$2.22 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $111,632 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $111,069 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,252 | $900 |
$1,252
20,223
kWh
|
|
| 02 | 2.3212: Optimize plant power factor | $37,071 | $47,040 |
$37,071
-
kWh
|
|
| 03 | 2.4221: Install compressor air intakes in coolest locations | $3,317 | $2,000 |
$3,317
53,927
kWh
|
|
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $371 | $900 |
$371
6,155
kWh
|
|
| 05 | 2.6218: Turn off equipment when not in use | $192 | - |
$192
3,224
kWh
|
|
| 06 | 2.4133: Use most efficient type of electric motors | $67,735 | $44,850 |
$67,735
1,101,114
kWh
|
|
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,694 | $934 |
$1,694
27,550
kWh
|
|
| TOTAL RECOMMENDED | $111,632 | $96,624 |
$111,632
1,212,193
kWh
|
||
| TOTAL IMPLEMENTED | $111,069 | $95,724 |
$111,069
1,202,814
kWh
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs