| Assessment Year | 1994 |
|---|---|
| Principal Product | metal dies |
| NAICS |
n/a
|
| SIC | 3544: Special Dies and Tools, Die Sets, Jigs and Fixtures, and Industrial Molds |
| Sales Range | $50 M to 100M |
| # of Employees | 640 |
| Plant Area |
430,000
ft2
|
| Annual Production | 450
pieces
|
| Production Hrs. Annual | 4,080
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $993,990 | 18,250,000 |
kWh
|
$0.054 |
| Natural Gas | $38,222 | 8,089 |
MMBtu
|
$4.73 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $61,159 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $57,167 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $39,102 | $3,900 |
$39,102
681,419
kWh
|
|
| 02 | 2.4133: Use most efficient type of electric motors | $14,959 | $25,920 |
$14,959
274,619
kWh
|
|
| 03 | 2.7135: Install occupancy sensors | $3,537 | $800 |
$3,537
65,064
kWh
|
|
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,719 | $2,179 |
$1,719
31,653
kWh
|
|
| 05 | 2.4221: Install compressor air intakes in coolest locations | $1,387 | $1,850 |
$1,387
25,498
kWh
|
|
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $455 | $1,330 |
$455
8,499
kWh
|
|
| TOTAL RECOMMENDED | $61,159 | $35,979 |
$61,159
1,086,752
kWh
|
||
| TOTAL IMPLEMENTED | $57,167 | $33,849 |
$57,167
1,013,189
kWh
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs