ITAC Assessment: ND0184
ITAC logo
ITAC Assessment: ND0184
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product hydraulic and pneumatic cylinders
NAICS
n/a
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 85
Plant Area 70,000
ft2
Annual Production 20,000
pieces
Production Hrs. Annual 4,539
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $67,148 845,545
kWh
Natural Gas $27,036 5,333
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $20,498 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,465

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4133: Use most efficient type of electric motors $13,418 $9,845 $13,418
168,816
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,206 $927 $4,206
53,048
kWh
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,585 $660 $1,585
19,930
kWh
-
04 2.7491: Insulate glazing, walls, ceilings, and roofs $567 $375 - $567
-
MMBtu
05 2.7447: Install vinyl strip / high speed / air curtain doors $317 $580 - $317
-
MMBtu
06 2.7444: Close holes and openings in building such as broken windows $256 $500 - $256
-
MMBtu
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $149 - $149
1,758
kWh
-
TOTAL RECOMMENDED $20,498 $12,887 $19,358
243,552
kWh
$1,140
-
MMBtu
TOTAL IMPLEMENTED $19,465 $11,932 $19,209
241,794
kWh
$256
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs