Assessment Year | 2018 |
---|---|
Principal Product | Formaldehyde resins and adhesives |
NAICS | 325211: Plastics Material and Resin Manufacturing |
SIC | 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers |
Sales Range | $50 M to 100M |
# of Employees | 55 |
Plant Area |
348,480
ft2
|
Annual Production | 100,000,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $468,045 | 10,783,720 |
kWh
|
$0.043 | |
Electricity Demand | $121,416 | 20,496 |
kW-mo/yr
|
$5.92 | |
Electricity Fees | $4,842 | - |
|
- | |
Natural Gas | $185,362 | 71,395 |
MMBtu
|
$2.60 | |
Waste Disposal Costs | |||||
Water Usage | $123,067 | 55,010 |
Tgal
|
$2.24 | |
TOTAL YEARLY COSTS | $902,732 | ||||
RECOMMENDED SAVINGS* | $45,490 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $21,406 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings | Primary Raw Material Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2135: Repair and eliminate steam leaks | $12,552 | $1,970 | - | - |
$3,630
-
MMBtu
|
$4,629
-
Tgal
|
- | - |
$4,293
-
Tgal
|
|
02 | 2.2628: Utilize a less expensive cooling method | $15,952 | $28,542 |
$2,347
44,834
kWh
|
$405
-
kW-mo/yr
|
- | - | $13,200 | - | - | |
03 | 2.2414: Use waste heat from hot flue gases to preheat | $6,311 | $2,097 | - | - |
$6,311
-
MMBtu
|
- | - | - | - | |
04 | 4.131: Modify process to reduce material use/cost | $8,000 | $24,775 | - | - | - | - | - | $8,000 | - | |
05 | 2.5123: Reduce fluid flow rates | $1,821 | $3,221 |
$1,821
42,050
kWh
|
- | - | - | - | - | - | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $854 | - |
$407
9,399
kWh
|
$447
-
kW-mo/yr
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $45,490 | $60,605 |
$4,575
96,283
kWh
|
$852
-
kW-mo/yr
|
$9,941
-
MMBtu
|
$4,629
-
Tgal
|
$13,200 | $8,000 |
$4,293
-
Tgal
|
||
TOTAL IMPLEMENTED | $21,406 | $26,745 |
$407
9,399
kWh
|
$447
-
kW-mo/yr
|
$3,630
-
MMBtu
|
$4,629
-
Tgal
|
- | $8,000 |
$4,293
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings | Primary Raw Material Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs