ITAC Assessment: OR0706
ITAC logo
ITAC Assessment: OR0706
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Formaldehyde resins and adhesives
NAICS 325211: Plastics Material and Resin Manufacturing
SIC 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers
Sales Range $50
M
to 100
M
# of Employees 55
Plant Area 348,480
ft2
Annual Production 100,000,000
units
Production Hrs. Annual 8,760
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $468,045 10,783,720
kWh
Electricity Demand $121,416 20,496
kW-mo/yr
Electricity Fees $4,842 -
Natural Gas $185,362 71,395
MMBtu
Waste Disposal Costs
Water Usage $123,067 55,010
Tgal
TOTAL YEARLY COSTS $902,732
RECOMMENDED SAVINGS* $45,490 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $21,406

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings Primary Raw Material Savings Water Consumption Savings
01 2.2135: Repair and eliminate steam leaks $12,552 $1,970 - - $3,630
-
MMBtu
$4,629
-
Tgal
- - $4,293
-
Tgal
02 2.2628: Utilize a less expensive cooling method $15,952 $28,542 $2,347
44,834
kWh
$405
-
kW-mo/yr
- - $13,200 - -
03 2.2414: Use waste heat from hot flue gases to preheat $6,311 $2,097 - - $6,311
-
MMBtu
- - - -
04 4.131: Modify process to reduce material use/cost $8,000 $24,775 - - - - - $8,000 -
05 2.5123: Reduce fluid flow rates $1,821 $3,221 $1,821
42,050
kWh
- - - - - -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $854 - $407
9,399
kWh
$447
-
kW-mo/yr
- - - - -
TOTAL RECOMMENDED $45,490 $60,605 $4,575
96,283
kWh
$852
-
kW-mo/yr
$9,941
-
MMBtu
$4,629
-
Tgal
$13,200 $8,000 $4,293
-
Tgal
TOTAL IMPLEMENTED $21,406 $26,745 $407
9,399
kWh
$447
-
kW-mo/yr
$3,630
-
MMBtu
$4,629
-
Tgal
- $8,000 $4,293
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings Primary Raw Material Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs