Assessment Year | 2006 |
---|---|
Principal Product | frozen bread foods |
NAICS | 311812: Commercial Bakeries |
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | $50 M to 100M |
# of Employees | 460 |
Plant Area |
147,000
ft2
|
Annual Production | 101,000,000
lb
|
Production Hrs. Annual | 4,745
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,090,288 | 15,009,600 |
kWh
|
$0.073 |
Electricity Demand | $306,536 | 30,048 |
kW-mo/yr
|
$10.20 |
Natural Gas | $514,814 | 41,488 |
MMBtu
|
$12.41 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $108,330 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $104,586 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $35,284 | $80,876 |
$29,572
407,334
kWh
|
$5,712
-
kW-mo/yr
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $29,328 | $36,752 |
$24,584
338,624
kWh
|
$4,744
-
kW-mo/yr
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $27,880 | $49,394 |
$23,372
321,939
kWh
|
$4,508
-
kW-mo/yr
|
|
04 | 2.4133: Use most efficient type of electric motors | $7,788 | $13,700 |
$5,748
200,613
kWh
|
$2,040
-
kW-mo/yr
|
|
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,306 | - |
$4,306
59,314
kWh
|
- | |
06 | 2.7135: Install occupancy sensors | $3,744 | $1,280 |
$3,744
51,576
kWh
|
- | |
TOTAL RECOMMENDED | $108,330 | $182,002 |
$91,326
1,379,400
kWh
|
$17,004
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $104,586 | $180,722 |
$87,582
1,327,824
kWh
|
$17,004
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs