ITAC Assessment: ND0179
ITAC logo
ITAC Assessment: ND0179
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Flow meters
NAICS
n/a
SIC 3823: Industrial Instruments for Measurement, Display, and Control of Process Variables; and Related Products
Sales Range $5
M
to 10
M
# of Employees 120
Plant Area 33,000
ft2
Annual Production 4,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $54,206 1,098,476
kWh
Natural Gas $4,069 715
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,319 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,556 $382 $2,556
51,876
kWh
02 2.7135: Install occupancy sensors $4,152 $3,605 $4,152
84,115
kWh
03 2.4221: Install compressor air intakes in coolest locations $224 $50 $224
4,689
kWh
04 2.4133: Use most efficient type of electric motors $8,323 $1,200 $8,323
168,523
kWh
05 2.7142: Utilize higher efficiency lamps and/or ballasts $64 $210 $64
1,172
kWh
TOTAL RECOMMENDED $15,319 $5,447 $15,319
310,375
kWh
TOTAL IMPLEMENTED - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs