ITAC Assessment: ND0043
ITAC logo
ITAC Assessment: ND0043
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product CONVEYOR BELTS
NAICS
n/a
SIC 3052: Rubber and Plastics Hose and Belting
Sales Range $5
M
to 10
M
# of Employees 59
Plant Area
n/a
Annual Production 12,000
pieces
Production Hrs. Annual 4,290
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $39,808 587,339
kWh
Natural Gas $14,632 2,932
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,105 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,856

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,311 $948 $1,562
23,154
kWh
- $(-251.0)
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,269 $300 $2,269
33,411
kWh
- -
03 2.4133: Use most efficient type of electric motors $212 $3,350 $212
3,224
kWh
- -
04 2.7444: Close holes and openings in building such as broken windows $249 $120 $20
293
kWh
$229
-
MMBtu
-
05 2.7492: Use proper thickness of insulation on building envelope $64 $160 - $64
-
MMBtu
-
TOTAL RECOMMENDED $4,105 $4,878 $4,063
60,082
kWh
$293
-
MMBtu
$(-251.0)
TOTAL IMPLEMENTED $3,856 $4,758 $4,043
59,789
kWh
$64
-
MMBtu
$(-251.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs