Assessment Year | 1991 |
---|---|
Principal Product | PROCESSED RUBBER |
NAICS |
n/a
|
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 75 |
Plant Area |
n/a
|
Annual Production | 27,500,000
lb
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $216,630 | 4,121,923 |
kWh
|
$0.053 |
Natural Gas | $11,084 | 2,033 |
MMBtu
|
$5.45 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $51,927 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|
01 | 3.4115: Recover and reuse cooling water | $34,109 | - |
$4,109
78,253
kWh
|
$30,000 | |
02 | 2.4322: Use or replace with energy efficient substitutes | $11,044 | $2,898 |
$11,044
210,141
kWh
|
- | |
03 | 2.4322: Use or replace with energy efficient substitutes | $3,738 | $6,000 |
$3,738
71,219
kWh
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $104 | $70 |
$104
2,052
kWh
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,617 | $397 |
$1,617
30,774
kWh
|
- | |
06 | 2.7122: Disconnect ballasts | $65 | $115 |
$65
1,172
kWh
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,250 | $6,111 |
$1,250
23,740
kWh
|
- | |
TOTAL RECOMMENDED | $51,927 | $15,591 |
$21,927
417,351
kWh
|
$30,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs