ITAC Assessment: NC0668
ITAC logo
ITAC Assessment: NC0668
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Office furniture
NAICS 337211: Wood Office Furniture Manufacturing
SIC 2521: Wood Office Furniture
Sales Range $10
M
to 50
M
# of Employees 126
Plant Area 194,500
ft2
Annual Production 50,000
pieces
Production Hrs. Annual 2,200
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $103,299 1,562,220
kWh
Electricity Demand $27,640 7,438
kW-mo/yr
Natural Gas $57,844 7,135
MMBtu
Waste Disposal Costs
Water Usage $1 1
Tgal
TOTAL YEARLY COSTS $188,784
RECOMMENDED SAVINGS* $14,009 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,512 $5,587 $1,922
29,076
kWh
$590
-
kW-mo/yr
-
02 2.7135: Install occupancy sensors $69 $280 $69
1,037
kWh
- -
03 2.2437: Recover waste heat from equipment $2,314 $8,000 - - $2,314
-
MMBtu
04 2.6218: Turn off equipment when not in use $2,843 $6,325 $1,158
17,518
kWh
- $1,685
-
MMBtu
05 2.4226: Use / purchase optimum sized compressor $6,271 $22,000 $4,799
72,600
kWh
$1,472
-
kW-mo/yr
-
TOTAL RECOMMENDED $14,009 $42,192 $7,948
120,231
kWh
$2,062
-
kW-mo/yr
$3,999
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs