| Assessment Year | 2016 |
|---|---|
| Principal Product | Semiconductor Manufacturing |
| NAICS | 334413: Semiconductor and Related Device Manufacturing |
| SIC | 3674: Semiconductors and Related Devices |
| Sales Range | $10 M to 50M |
| # of Employees | 400 |
| Plant Area |
300,000
ft2
|
| Annual Production | 172,000
pieces
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $3,303,209 | 63,358,800 |
kWh
|
$0.052 | |
| Electricity Demand | $716,393 | 98,868 |
kW-mo/yr
|
$7.25 | |
| Natural Gas | $261,238 | 78,524 |
MMBtu
|
$3.33 | |
| Waste Disposal Costs | |||||
| Water Usage | $504,620 | 89,662,000 |
Tgal
|
$0.006 | |
| TOTAL YEARLY COSTS | $4,785,460 | ||||
| RECOMMENDED SAVINGS* | $565,852 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $5,339 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $3,767 | $3,112 |
$3,767
72,445
kWh
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $17,283 | $8,000 |
$17,283
332,369
kWh
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $972 | $4,623 |
$815
15,673
kWh
|
$157
-
kW-mo/yr
|
- | |
| 04 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $73,902 | $31,000 |
$73,902
1,421,200
kWh
|
- | - | |
| 05 | 2.4322: Use or replace with energy efficient substitutes | $600 | $3,450 |
$500
9,617
kWh
|
$100
-
kW-mo/yr
|
- | |
| 06 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $469,328 | $2,302,430 | - | - | $469,328 | |
| TOTAL RECOMMENDED | $565,852 | $2,352,615 |
$96,267
1,851,304
kWh
|
$257
-
kW-mo/yr
|
$469,328 | ||
| TOTAL IMPLEMENTED | $5,339 | $11,185 |
$5,082
97,735
kWh
|
$257
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs