ITAC Assessment: NC0665
ITAC logo
ITAC Assessment: NC0665
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Friction paper
NAICS 322299: All Other Converted Paper Product Manufacturing
SIC 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 32
Plant Area 150,000
ft2
Annual Production 50,000
thousand feet
Production Hrs. Annual 4,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $163,582 2,375,200
kWh
Electricity Demand $48,275 9,932
kW-mo/yr
Natural Gas $121,395 24,475
MMBtu
Waste Disposal Costs
Water Usage $2,740 455
Tgal
TOTAL YEARLY COSTS $335,992
RECOMMENDED SAVINGS* $12,741 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4226: Use / purchase optimum sized compressor $6,027 - $3,963
56,700
kWh
$2,064
-
kW-mo/yr
-
02 2.2437: Recover waste heat from equipment $1,072 $1,000 - - $1,072
-
MMBtu
03 2.2437: Recover waste heat from equipment $5,642 $2,000 - - $5,642
-
MMBtu
TOTAL RECOMMENDED $12,741 $3,000 $3,963
56,700
kWh
$2,064
-
kW-mo/yr
$6,714
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs