| Assessment Year | 2021 |
|---|---|
| Principal Product | Friction paper |
| NAICS | 322299: All Other Converted Paper Product Manufacturing |
| SIC | 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 32 |
| Plant Area |
150,000
ft2
|
| Annual Production | 50,000
thousand feet
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $163,582 | 2,375,200 |
kWh
|
$0.069 | |
| Electricity Demand | $48,275 | 9,932 |
kW-mo/yr
|
$4.86 | |
| Natural Gas | $121,395 | 24,475 |
MMBtu
|
$4.96 | |
| Waste Disposal Costs | |||||
| Water Usage | $2,740 | 455 |
Tgal
|
$6.02 | |
| TOTAL YEARLY COSTS | $335,992 | ||||
| RECOMMENDED SAVINGS* | $12,741 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4226: Use / purchase optimum sized compressor | $6,027 | - |
$3,963
56,700
kWh
|
$2,064
-
kW-mo/yr
|
- | |
| 02 | 2.2437: Recover waste heat from equipment | $1,072 | $1,000 | - | - |
$1,072
-
MMBtu
|
|
| 03 | 2.2437: Recover waste heat from equipment | $5,642 | $2,000 | - | - |
$5,642
-
MMBtu
|
|
| TOTAL RECOMMENDED | $12,741 | $3,000 |
$3,963
56,700
kWh
|
$2,064
-
kW-mo/yr
|
$6,714
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs