| Assessment Year | 2019 |
|---|---|
| Principal Product | Fiberglass veil |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3229: Pressed and Blown Glass and Glassware, Not Elsewhere Classified |
| Sales Range | $100 M to 500M |
| # of Employees | 100 |
| Plant Area |
195,000
ft2
|
| Annual Production | 30,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $394,337 | 13,330,383 |
kWh
|
$0.030 |
| Electricity Demand | $277,603 | 25,608 |
kW-mo/yr
|
$10.84 |
| Natural Gas | $880,462 | 241,440 |
MMBtu
|
$3.65 |
| TOTAL YEARLY COSTS | $1,552,402 | |||
| RECOMMENDED SAVINGS* | $62,440 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,243 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,243 | $610 |
$1,493
50,456
kWh
|
$750
-
kW-mo/yr
|
- | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,106 | $100 |
$736
24,878
kWh
|
$370
-
kW-mo/yr
|
- | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $281 | $750 |
$281
9,483
kWh
|
- | - | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $8,371 | $5,000 |
$5,575
188,340
kWh
|
$2,796
-
kW-mo/yr
|
- | |
| 05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,460 | $1,000 | - | - |
$2,460
-
MMBtu
|
|
| 06 | 2.2136: Install / repair insulation on steam lines | $329 | $250 | - | - |
$329
-
MMBtu
|
|
| 07 | 2.2437: Recover waste heat from equipment | $35,842 | $115,000 |
$(-3,812.0)
(-128,772)
kWh
|
$(-1,912.0)
-
kW-mo/yr
|
$41,566
-
MMBtu
|
|
| 08 | 2.4154: Avoid rewinding motors more than twice | $11,808 | $25,282 |
$7,863
265,642
kWh
|
$3,945
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $62,440 | $147,992 |
$12,136
410,027
kWh
|
$5,949
-
kW-mo/yr
|
$44,355
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $2,243 | $610 |
$1,493
50,456
kWh
|
$750
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs