ITAC Assessment: NC0629
ITAC logo
ITAC Assessment: NC0629
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Fiberglass veil
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3229: Pressed and Blown Glass and Glassware, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 100
Plant Area 195,000
ft2
Annual Production 30,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $394,337 13,330,383
kWh
Electricity Demand $277,603 25,608
kW-mo/yr
Natural Gas $880,462 241,440
MMBtu
TOTAL YEARLY COSTS $1,552,402
RECOMMENDED SAVINGS* $62,440 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,243

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,243 $610 $1,493
50,456
kWh
$750
-
kW-mo/yr
-
02 2.4231: Reduce the pressure of compressed air to the minimum required $1,106 $100 $736
24,878
kWh
$370
-
kW-mo/yr
-
03 2.4231: Reduce the pressure of compressed air to the minimum required $281 $750 $281
9,483
kWh
- -
04 2.4231: Reduce the pressure of compressed air to the minimum required $8,371 $5,000 $5,575
188,340
kWh
$2,796
-
kW-mo/yr
-
05 2.1233: Analyze flue gas for proper air/fuel ratio $2,460 $1,000 - - $2,460
-
MMBtu
06 2.2136: Install / repair insulation on steam lines $329 $250 - - $329
-
MMBtu
07 2.2437: Recover waste heat from equipment $35,842 $115,000 $(-3,812.0)
(-128,772)
kWh
$(-1,912.0)
-
kW-mo/yr
$41,566
-
MMBtu
08 2.4154: Avoid rewinding motors more than twice $11,808 $25,282 $7,863
265,642
kWh
$3,945
-
kW-mo/yr
-
TOTAL RECOMMENDED $62,440 $147,992 $12,136
410,027
kWh
$5,949
-
kW-mo/yr
$44,355
-
MMBtu
TOTAL IMPLEMENTED $2,243 $610 $1,493
50,456
kWh
$750
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs