ITAC Assessment: NC0624
ITAC logo
ITAC Assessment: NC0624
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Oriented Strand Board
NAICS 321219: Reconstituted Wood Product Manufacturing
SIC 2493: Reconstituted Wood Products
Sales Range $100
M
to 500
M
# of Employees 151
Plant Area 300,000
ft2
Annual Production 520,000
thousand feet
Production Hrs. Annual 8,736
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,882,112 61,368,737
kWh
Electricity Demand $1,556,106 97,260
kW-mo/yr
Natural Gas $927,500 232,000
MMBtu
Wood $1 2,200,000
MMBtu
TOTAL YEARLY COSTS $5,365,719
RECOMMENDED SAVINGS* $92,391 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $37,704 $24,212 $25,746
546,624
kWh
$11,958
-
kW-mo/yr
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,403 $200 $7,623
161,842
kWh
$3,540
-
kW-mo/yr
- $(-2,880.0) $(-2,880.0)
03 2.4231: Reduce the pressure of compressed air to the minimum required $107 $450 $107
2,282
kWh
- - - -
04 2.4154: Avoid rewinding motors more than twice $39,622 $58,313 $27,055
574,424
kWh
$12,567
-
kW-mo/yr
- - -
05 2.1135: Repair furnaces and oven doors so that they seal efficiently $9,555 $2,000 - - $9,555
-
MMBtu
- -
TOTAL RECOMMENDED $92,391 $85,175 $60,531
1,285,172
kWh
$28,065
-
kW-mo/yr
$9,555
-
MMBtu
$(-2,880.0) $(-2,880.0)
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs