| Assessment Year | 2018 |
|---|---|
| Principal Product | Fabrics |
| NAICS | 336360: Motor Vehicle Seating and Interior Trim Manufacturing |
| SIC | 2396: Automotive Trimmings, Apparel Findings, and Related Products |
| Sales Range | $10 M to 50M |
| # of Employees | 125 |
| Plant Area |
300,000
ft2
|
| Annual Production | 11,000
thousand feet
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $627,886 | 11,941,445 |
kWh
|
$0.053 | |
| Electricity Demand | $223,086 | 22,601 |
kW-mo/yr
|
$9.87 | |
| Natural Gas | $717,426 | 158,263 |
MMBtu
|
$4.53 | |
| Waste Disposal Costs | |||||
| Water Usage | $521,992 | 253,584 |
Tgal
|
$2.06 | |
| TOTAL YEARLY COSTS | $2,090,390 | ||||
| RECOMMENDED SAVINGS* | $66,371 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $12,921 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,801 | $500 |
$2,529
45,160
kWh
|
$776
-
kW-mo/yr
|
- | - | $(-480.0) | $(-24.0) | |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $1,322 | $900 |
$1,322
23,615
kWh
|
- | - | - | - | - | |
| 03 | 2.2136: Install / repair insulation on steam lines | $2,320 | $1,203 | - | - |
$2,320
-
MMBtu
|
- | - | - | |
| 04 | 3.1191: Change procedures / equipment / operating conditions | $6,478 | $16,800 |
$(-580.0)
(-10,350)
kWh
|
$(-422.0)
-
kW-mo/yr
|
- |
$32,480
-
Tgal
|
$(-25,000.0) | - | |
| 05 | 2.7241: Install outside air damper / economizer on hvac unit | $14,884 | $10,000 |
$14,884
265,790
kWh
|
- | - | - | - | - | |
| 06 | 2.4154: Avoid rewinding motors more than twice | $38,566 | $70,014 |
$29,512
526,997
kWh
|
$9,054
-
kW-mo/yr
|
- | - | - | - | |
| TOTAL RECOMMENDED | $66,371 | $99,417 |
$47,667
851,212
kWh
|
$9,408
-
kW-mo/yr
|
$2,320
-
MMBtu
|
$32,480
-
Tgal
|
$(-25,480.0) | $(-24.0) | ||
| TOTAL IMPLEMENTED | $12,921 | $19,403 |
$3,271
58,425
kWh
|
$354
-
kW-mo/yr
|
$2,320
-
MMBtu
|
$32,480
-
Tgal
|
$(-25,480.0) | $(-24.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs