Assessment Year | 2018 |
---|---|
Principal Product | School bus seating |
NAICS | 336999: All Other Transportation Equipment Manufacturing |
SIC | 3799: Transportation Equipment, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 233 |
Plant Area |
140,000
ft2
|
Annual Production | 315,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $194,126 | 3,298,123 |
kWh
|
$0.059 |
Electricity Demand | $37,387 | 8,724 |
kW-mo/yr
|
$4.29 |
Natural Gas | $143,493 | 18,879 |
MMBtu
|
$7.60 |
TOTAL YEARLY COSTS | $375,006 | |||
RECOMMENDED SAVINGS* | $52,993 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $34,610 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,812 | $46,617 |
$11,930
202,553
kWh
|
$1,882
-
kW-mo/yr
|
- | - | - | |
02 | 2.7135: Install occupancy sensors | $481 | $250 |
$481
8,164
kWh
|
- | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,414 | $525 |
$4,287
72,798
kWh
|
$652
-
kW-mo/yr
|
- | $(-360.0) | $(-165.0) | |
04 | 2.4239: Eliminate or reduce compressed air usage | $161 | $450 |
$161
2,736
kWh
|
- | - | - | - | |
05 | 2.4226: Use / purchase optimum sized compressor | $1,361 | $6,000 |
$935
15,880
kWh
|
$426
-
kW-mo/yr
|
- | - | - | |
06 | 2.2437: Recover waste heat from equipment | $4,913 | $8,000 | - | - |
$4,913
-
MMBtu
|
- | - | |
07 | 2.7243: Improve air circulation with destratification fans / other methods | $1,221 | $1,000 |
$1,060
18,000
kWh
|
$161
-
kW-mo/yr
|
- | - | - | |
08 | 2.7241: Install outside air damper / economizer on hvac unit | $10,727 | $28,500 |
$10,727
182,130
kWh
|
- | - | - | - | |
09 | 2.8114: Change rate schedules or other changes in utility service | $15,903 | $500 |
$15,903
-
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $52,993 | $91,842 |
$45,484
502,261
kWh
|
$3,121
-
kW-mo/yr
|
$4,913
-
MMBtu
|
$(-360.0) | $(-165.0) | ||
TOTAL IMPLEMENTED | $34,610 | $47,892 |
$32,601
283,515
kWh
|
$2,534
-
kW-mo/yr
|
- | $(-360.0) | $(-165.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs