| Assessment Year | 2005 |
|---|---|
| Principal Product | Juices, dressings, and sauces |
| NAICS | 311941: Mayonnaise, Dressing, and Other Prepared Sauce Manufacturing |
| SIC | 2035: Pickled Fruits and Vegetables, Vegetable Sauces and Seasonings, and Salad Dressings |
| Sales Range | $50 M to 100M |
| # of Employees | 138 |
| Plant Area |
110,000
ft2
|
| Annual Production | 200,000,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Iowa |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $98,980 | 2,928,623 |
kWh
|
$0.034 |
| Electricity Demand | $37,125 | 6,496 |
kW-mo/yr
|
$5.72 |
| Electricity Fees | $5,559 | - |
|
- |
| Natural Gas | $244,690 | 33,509 |
MMBtu
|
$7.30 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $32,310 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,051 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3191: Use demand controller or load shedder | $15,800 | $6,352 | - |
$800
-
kW-mo/yr
|
- | - | $15,000 | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $774 | $76 |
$414
19,842
kWh
|
$360
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4239: Eliminate or reduce compressed air usage | $6,024 | $790 |
$3,221
154,128
kWh
|
$2,803
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4224: Upgrade controls on compressors | $3,593 | $500 |
$761
36,400
kWh
|
- | - | $2,832 | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $518 | $30,000 |
$277
13,292
kWh
|
$241
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.7135: Install occupancy sensors | $299 | $504 |
$299
14,283
kWh
|
- | - | - | - | |
| 07 | 2.1133: Adjust burners for efficient operation | $1,436 | $1,000 | - | - |
$1,436
-
MMBtu
|
- | - | |
| 08 | 4.514: Re-arrange equipment layout to reduce handling costs | $3,866 | $1,223 | - | - | - | $3,866 | - | |
| TOTAL RECOMMENDED | $32,310 | $40,445 |
$4,972
237,945
kWh
|
$4,204
-
kW-mo/yr
|
$1,436
-
MMBtu
|
$6,698 | $15,000 | ||
| TOTAL IMPLEMENTED | $9,051 | $32,370 |
$4,211
201,545
kWh
|
$3,404
-
kW-mo/yr
|
$1,436
-
MMBtu
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs