Assessment Year | 2018 |
---|---|
Principal Product | Wood siding |
NAICS | 321113: Sawmills |
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $100 M to 500M |
# of Employees | 400 |
Plant Area |
472,000
ft2
|
Annual Production | 377,268,000
lb
|
Production Hrs. Annual | 8,232
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $4,481,676 | 118,667,000 |
kWh
|
$0.038 |
Electricity Demand | $1,795,995 | 203,443 |
kW-mo/yr
|
$8.83 |
Natural Gas | $64,442 | 8,383 |
MMBtu
|
$7.69 |
LPG | $689,025 | 81,467 |
MMBtu
|
$8.46 |
Wood | $2,834,662 | 1,704,780 |
MMBtu
|
$1.66 |
TOTAL YEARLY COSTS | $9,865,800 | |||
RECOMMENDED SAVINGS* | $404,071 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $198,301 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Wood Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $48,456 | $119,341 |
$30,326
802,278
kWh
|
$10,844
-
kW-mo/yr
|
- | - | - | $7,286 | |
02 | 2.7135: Install occupancy sensors | $369 | $547 |
$369
9,773
kWh
|
- | - | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,868 | $20,154 |
$6,630
175,388
kWh
|
- | - | - | - | $1,238 | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,634 | $200 |
$2,564
67,832
kWh
|
$870
-
kW-mo/yr
|
- | - | $(-800.0) | $(-1,000.0) | |
05 | 2.3413: Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat | $48,482 | $180,000 |
$84,974
2,248,000
kWh
|
$29,674
-
kW-mo/yr
|
$(-66,166.0)
-
MMBtu
|
- | - | - | |
06 | 2.3413: Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat | $21,044 | $500 |
$45,965
1,216,000
kWh
|
$16,051
-
kW-mo/yr
|
$(-40,972.0)
-
MMBtu
|
- | - | - | |
07 | 2.2121: Increase amount of condensate returned | $205,770 | $100,000 | - | - | - |
$137,770
-
MMBtu
|
- | $68,000 | |
08 | 2.2113: Repair or replace steam traps | $11,945 | $10,500 | - | - | - |
$26,945
-
MMBtu
|
$(-2,500.0) | $(-12,500.0) | |
09 | 2.5194: Redesign process | $31,091 | $15,000 |
$23,213
614,107
kWh
|
$7,878
-
kW-mo/yr
|
- | - | - | - | |
10 | 2.4151: Develop a repair/replace policy | $27,412 | $65,590 |
$20,466
541,440
kWh
|
$6,946
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $404,071 | $511,832 |
$214,507
5,674,818
kWh
|
$72,263
-
kW-mo/yr
|
$(-107,138.0)
-
MMBtu
|
$164,715
-
MMBtu
|
$(-3,300.0) | $63,024 | ||
TOTAL IMPLEMENTED | $198,301 | $411,832 |
$214,507
5,674,818
kWh
|
$72,263
-
kW-mo/yr
|
$(-107,138.0)
-
MMBtu
|
$26,945
-
MMBtu
|
$(-3,300.0) | $(-4,976.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Wood Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs