Assessment Year | 2017 |
---|---|
Principal Product | Yarns |
NAICS | 313110: Fiber, Yarn, and Thread Mills |
SIC | 2281: Yarn Spinning Mills |
Sales Range | $1 M to 5M |
# of Employees | 110 |
Plant Area |
135,000
ft2
|
Annual Production | 25,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $463,064 | 11,598,000 |
kWh
|
$0.040 |
Electricity Demand | $256,141 | 22,666 |
kW-mo/yr
|
$11.30 |
TOTAL YEARLY COSTS | $719,205 | |||
RECOMMENDED SAVINGS* | $131,175 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $63,467 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $17,643 | $50,038 |
$8,818
220,990
kWh
|
$5,246
-
kW-mo/yr
|
- | $3,579 | |
02 | 2.7135: Install occupancy sensors | $40 | $100 |
$40
998
kWh
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,607 | $500 |
$4,002
100,296
kWh
|
$1,605
-
kW-mo/yr
|
$(-500.0) | $(-500.0) | |
04 | 2.4239: Eliminate or reduce compressed air usage | $74 | $240 |
$74
1,864
kWh
|
- | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,221 | $100 |
$2,300
57,624
kWh
|
$921
-
kW-mo/yr
|
- | - | |
06 | 2.4226: Use / purchase optimum sized compressor | $21,836 | $50 |
$12,616
316,201
kWh
|
$9,220
-
kW-mo/yr
|
- | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $64,413 | $100,000 |
$44,754
1,121,648
kWh
|
$19,659
-
kW-mo/yr
|
- | - | |
08 | 2.7241: Install outside air damper / economizer on hvac unit | $19,341 | $30,000 |
$19,341
484,733
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $131,175 | $181,028 |
$91,945
2,304,354
kWh
|
$36,651
-
kW-mo/yr
|
$(-500.0) | $3,079 | ||
TOTAL IMPLEMENTED | $63,467 | $80,688 |
$44,817
1,123,218
kWh
|
$16,071
-
kW-mo/yr
|
$(-500.0) | $3,079 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs