ITAC Assessment: NC0599
ITAC logo
ITAC Assessment: NC0599
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Electronic switches
NAICS 334419: Other Electronic Component Manufacturing
SIC 3679: Electronic Components, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 58
Plant Area 55,000
ft2
Annual Production 300,000
units
Production Hrs. Annual 2,100
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $81,303 1,563,040
kWh
Electricity Demand $38,716 4,307
kW-mo/yr
Natural Gas $3,514 468
MMBtu
TOTAL YEARLY COSTS $123,533
RECOMMENDED SAVINGS* $23,567 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,833

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $13,256 $36,992 $6,506
125,122
kWh
$5,212
-
kW-mo/yr
- - $1,538
02 2.7135: Install occupancy sensors $300 $1,500 $300
5,775
kWh
- - - -
03 2.2437: Recover waste heat from equipment $1,262 $500 - - $1,262
-
MMBtu
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,240 $200 $1,957
37,632
kWh
$483
-
kW-mo/yr
- $(-100.0) $(-100.0)
05 2.4239: Eliminate or reduce compressed air usage $2,472 $2,940 $2,472
47,530
kWh
- - - -
06 2.4151: Develop a repair/replace policy $4,037 $13,627 $2,255
43,361
kWh
$1,782
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $23,567 $55,759 $13,490
259,420
kWh
$7,477
-
kW-mo/yr
$1,262
-
MMBtu
$(-100.0) $1,438
TOTAL IMPLEMENTED $19,833 $52,319 $11,018
211,890
kWh
$7,477
-
kW-mo/yr
- $(-100.0) $1,438
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs