ITAC Assessment: NC0594
ITAC logo
ITAC Assessment: NC0594
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Heat exchangers
NAICS 332410: Power Boiler and Heat Exchanger Manufacturing
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $50
M
to 100
M
# of Employees 200
Plant Area 2,000,000
ft2
Annual Production 200,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $401,701 9,232,919
kWh
Electricity Demand $231,422 20,564
kW-mo/yr
Natural Gas $68,039 13,845
MMBtu
TOTAL YEARLY COSTS $701,162
RECOMMENDED SAVINGS* $70,902 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $57,267

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $41,372 $77,272 $24,830
570,805
kWh
$13,053
-
kW-mo/yr
- - $3,489
02 2.7135: Install occupancy sensors $5,666 $2,982 $5,666
130,254
kWh
- - - -
03 2.4224: Upgrade controls on compressors $5,016 $8,200 $5,016
115,313
kWh
- - - -
04 2.4226: Use / purchase optimum sized compressor $2,502 $1,000 $2,502
69,316
kWh
- - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $979 $100 $909
20,894
kWh
$470
-
kW-mo/yr
- $(-200.0) $(-200.0)
06 2.4231: Reduce the pressure of compressed air to the minimum required $1,732 $50 $1,142
26,244
kWh
$590
-
kW-mo/yr
- - -
07 2.2437: Recover waste heat from equipment $2,917 $3,500 - - $2,917
-
MMBtu
- -
08 2.2437: Recover waste heat from equipment $10,457 $20,000 - - $10,457
-
MMBtu
- -
09 2.3132: Recharge batteries on during off-peak demand periods $261 $200 $261
-
kWh
- - - -
TOTAL RECOMMENDED $70,902 $113,304 $40,326
932,826
kWh
$14,113
-
kW-mo/yr
$13,374
-
MMBtu
$(-200.0) $3,289
TOTAL IMPLEMENTED $57,267 $89,604 $40,065
932,826
kWh
$14,113
-
kW-mo/yr
- $(-200.0) $3,289
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs