ITAC Assessment: NC0590
ITAC logo
ITAC Assessment: NC0590
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Boat engine testing
NAICS 333618: Other Engine Equipment Manufacturing
SIC 3519: Internal Combustion Engines, Not Elsewhere Classified
Sales Range less than $500
k
# of Employees 230
Plant Area 117,000
ft2
Annual Production 1
pieces
Production Hrs. Annual 3,625
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $91,398 1,527,171
kWh
Electricity Demand $28,437 4,436
kW-mo/yr
Electricity Fees $1,186 -
Natural Gas $11,701 1,590
MMBtu
Waste Disposal Costs
Water Usage $6,690 507,899
Tgal
TOTAL YEARLY COSTS $139,412
RECOMMENDED SAVINGS* $66,427 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,200

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Usage Savings Water Disposal Savings Ancillary Material Cost Savings
01 2.8114: Change rate schedules or other changes in utility service $37,015 $250 $30,834
1
kWh
$6,917
-
kW-mo/yr
$(-736.0) - - - -
02 2.7442: Keep doors and windows shut when not on use $3,356 - - - - $3,356
-
MMBtu
- - -
03 3.4116: Meter recycled water (to reduce sewer charges) $3,139 $4,200 - - - - - $3,259
-
Tgal
$(-120.0)
04 2.2437: Recover waste heat from equipment $15,073 $6,000 $496
8,560
kWh
$1,207
-
kW-mo/yr
- $11,698
-
MMBtu
$1,672
-
Tgal
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $3,529 $9,666 $2,225
26,613
kWh
$1,072
-
kW-mo/yr
- - - - $232
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,501 $6,171 $767
13,239
kWh
$423
-
kW-mo/yr
- - - - $311
07 2.4231: Reduce the pressure of compressed air to the minimum required $45 $100 $29
488
kWh
$16
-
kW-mo/yr
- - - - -
08 2.6213: Turn off steam / hot water lines leading to space heating units $48 $65 $40
684
kWh
$8
-
kW-mo/yr
- - - - -
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,273 $230 $832
9,957
kWh
$441
-
kW-mo/yr
- - - - -
10 2.4151: Develop a repair/replace policy $1,448 $5,865 $900
15,539
kWh
$548
-
kW-mo/yr
- - - - -
TOTAL RECOMMENDED $66,427 $32,547 $36,123
75,081
kWh
$10,632
-
kW-mo/yr
$(-736.0) $15,054
-
MMBtu
$1,672
-
Tgal
$3,259
-
Tgal
$423
TOTAL IMPLEMENTED $11,200 $22,097 $4,793
66,520
kWh
$2,508
-
kW-mo/yr
- $3,356
-
MMBtu
- - $543
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Usage Savings Water Disposal Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs