Assessment Year | 2017 |
---|---|
Principal Product | Boat engine testing |
NAICS | 333618: Other Engine Equipment Manufacturing |
SIC | 3519: Internal Combustion Engines, Not Elsewhere Classified |
Sales Range | less than $500 k |
# of Employees | 230 |
Plant Area |
117,000
ft2
|
Annual Production | 1
pieces
|
Production Hrs. Annual | 3,625
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $91,398 | 1,527,171 |
kWh
|
$0.060 | |
Electricity Demand | $28,437 | 4,436 |
kW-mo/yr
|
$6.41 | |
Electricity Fees | $1,186 | - |
|
- | |
Natural Gas | $11,701 | 1,590 |
MMBtu
|
$7.36 | |
Waste Disposal Costs | |||||
Water Usage | $6,690 | 507,899 |
Tgal
|
$0.013 | |
TOTAL YEARLY COSTS | $139,412 | ||||
RECOMMENDED SAVINGS* | $66,427 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $11,200 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $37,015 | $250 |
$30,834
1
kWh
|
$6,917
-
kW-mo/yr
|
$(-736.0) | - | - | - | - | |
02 | 2.7442: Keep doors and windows shut when not on use | $3,356 | - | - | - | - |
$3,356
-
MMBtu
|
- | - | - | |
03 | 3.4116: Meter recycled water (to reduce sewer charges) | $3,139 | $4,200 | - | - | - | - | - |
$3,259
-
Tgal
|
$(-120.0) | |
04 | 2.2437: Recover waste heat from equipment | $15,073 | $6,000 |
$496
8,560
kWh
|
$1,207
-
kW-mo/yr
|
- |
$11,698
-
MMBtu
|
$1,672
-
Tgal
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,529 | $9,666 |
$2,225
26,613
kWh
|
$1,072
-
kW-mo/yr
|
- | - | - | - | $232 | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,501 | $6,171 |
$767
13,239
kWh
|
$423
-
kW-mo/yr
|
- | - | - | - | $311 | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $45 | $100 |
$29
488
kWh
|
$16
-
kW-mo/yr
|
- | - | - | - | - | |
08 | 2.6213: Turn off steam / hot water lines leading to space heating units | $48 | $65 |
$40
684
kWh
|
$8
-
kW-mo/yr
|
- | - | - | - | - | |
09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,273 | $230 |
$832
9,957
kWh
|
$441
-
kW-mo/yr
|
- | - | - | - | - | |
10 | 2.4151: Develop a repair/replace policy | $1,448 | $5,865 |
$900
15,539
kWh
|
$548
-
kW-mo/yr
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $66,427 | $32,547 |
$36,123
75,081
kWh
|
$10,632
-
kW-mo/yr
|
$(-736.0) |
$15,054
-
MMBtu
|
$1,672
-
Tgal
|
$3,259
-
Tgal
|
$423 | ||
TOTAL IMPLEMENTED | $11,200 | $22,097 |
$4,793
66,520
kWh
|
$2,508
-
kW-mo/yr
|
- |
$3,356
-
MMBtu
|
- | - | $543 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs